Dubai Electricity and Water Authority (DEWA) had 615 million imperial gallons a day (MIGD) of installed desalination capacity at September 30, 2026, up from 495 MIGD at the end of 2025. That rise of 120 MIGD in nine months compares with 25 MIGD added across 2016–2025, when capacity moved from 470 MIGD to 495 MIGD.
A thin margin before 2026
Demand had been closing in on the fleet. DEWA reported system desalinated water demand of 161.505 billion imperial gallons in 2025, up 6.62%, with a daily peak of 487 million imperial gallons. Against 495 MIGD installed, that left 8 MIGD of headroom at the 2025 peak. Capacity at September 30, 2026 sits 128 MIGD above that peak.
Where the water comes from
At the end of 2025 the fleet was the Jebel Ali multi-stage flash plant (427 MIGD), Jebel Ali reverse osmosis (63 MIGD) and Palm Jumeirah reverse osmosis (5 MIGD). Hassyan reverse osmosis Block A added 60 MIGD in Q1 2026, taking capacity to 555 MIGD at March 31, 2026. DEWA's nine-month results do not name the plant behind the further 60 MIGD.
More capacity contracted
DEWA plans 735 MIGD by the end of 2030, of which 308 MIGD would be reverse osmosis running on renewable energy. In late October and early November 2026, DEWA and ACWA Power signed a 30-year, AED 1.76 billion agreement for a further 60 MIGD at Hassyan, with DEWA holding 60%. The full 180 MIGD Hassyan Phase 1 plant has two published completion dates, during 2026 and Q1 2027, and its completion has not been announced.
The full profile shows how the expansion sits alongside borrowings of AED 43,725.0 million at March 31, 2026, what DEWA's 2030 generation plan of more than 23 GW means for renewable-powered desalination, and which storage projects remain open. The full report, Utility Intelligence Profile: Dubai Electricity and Water Authority, is available for USD 99. For a free overview, read the Dubai Electricity and Water Authority Utility Snapshot.