DEWA had 615 million imperial gallons a day (MIGD) of desalination capacity installed at 30 September 2026, against 495 MIGD a year earlier. The 120 MIGD step came after a year in which peak demand ran close to installed capacity.
A narrow 2025
Daily peak demand for desalinated water reached 487 million imperial gallons in 2025, up 7.0% on the 455 reached in 2024. Capacity was still 495 MIGD in the third quarter of 2025, so the peak sat about 8 MIGD below what was installed. The resident population grew 7.5% in 2025 to 4.580 million.
Where the new capacity comes from
DEWA's capacity stood at 555 MIGD in the first quarter of 2026, after the first 60 MIGD block of the Hassyan seawater reverse osmosis plant entered service. Phase 1 at Hassyan totals 180 MIGD, was over 90% complete in early August 2026, and is due to be finished in the first quarter of 2027. A second phase of 60 MIGD, worth AED 1.76 billion, followed: ACWA Power disclosed its 30-year water purchase agreement on 28 October 2026.
What is still to come
DEWA's target is 735 MIGD by the end of 2030, which leaves 120 MIGD to add from the September 2026 level. Getting the Phase 2 water into the network depends on two pipeline packages: the lowest bids received in July 2026 were AED 335.92 million and AED 792.6 million, and neither had been awarded by 24 November 2026. Storage is the thinner buffer: the 882 million imperial gallons DEWA reported in 2024 equals about 1.8 days of the 2025 peak.
How much water does Dubai's system supply per resident, where do the sewerage tunnel concessions stand, and who approves the water tariff? The full report, Dubai Water Intelligence Report, is available for USD 799. For a free overview, see Dubai City Snapshot.