Metropolitan Water District of Southern California's share of the first stage of Pure Water Southern California is estimated at US$2,881 million, according to a September 2025 cost update. That is about 2.8 times the US$1.025 billion total Capital Investment Plan in the budget its Board adopted on April 14, 2026.
A plan funded to design, not construction
The Board certified the program's Final Environmental Impact Report on February 10, 2026. The adopted budget includes US$150 million for first-stage planning and final design. Construction had not been approved as of November 18, 2026.
The costs rise steeply with scale
The first stage would produce 45 million gallons a day at a total cost of US$3,578 million, shared with the Los Angeles County Sanitation Districts. At the full 150 million gallons a day, the estimate reaches US$11,315 million, of which Metropolitan's share is US$9,841 million, or 87%.
Grants cover a small slice
Grants secured by July 2025 totaled US$210 million, including US$80 million from the State of California and US$125 million from the Bureau of Reclamation. That is about 6% of the first stage's total cost. A federal WIFIA loan of up to 49% of project costs was under consideration.
Three dates for first water
Metropolitan has said first water could come "as early as 2033"; its program page shows operations beginning in 2032; and the September 2025 cost update puts the first stage online in 2035. Meanwhile debt service coverage on all senior and subordinate bonds fell from 2.09x in FY2021 to 1.14x in FY2024 before recovering to 2.45x in FY2025.
How Pure Water compares with Metropolitan's other supply decisions, what its imported sources face from 2027, and where its aging pipes and plants stand are set out in the report. The full report, Water Systems Overview: Metropolitan Water District of Southern California, is available for USD 499. For a free overview, read the Metropolitan Water District of Southern California Utility Snapshot.