The 820 km Al Mudhaibi distribution network in North Al Sharqiyah, worth about RO 65 million, was completed ahead of schedule in October 2026 on contractor-finance terms: the contractor paid for construction, and Nama Water Services repays it over five years after handover. A second package, worth about RO 15 million, was 45% complete.
Private money at several stages
Private capital appears elsewhere in the market too. The 300,000 m³-a-day Ghubrah III desalination plant in Muscat, 93% complete on 10 November 2026, reached financial close in January 2025 with US$370 million of project finance. The Wadi Dayqah purification plant, worth over OMR 55 million, is a 20-year build-own-operate concession. The Al Ansab and Al Amerat sewage plant expansions are build-own-operate-transfer partnerships, with bids due on 5 January 2027.
Operation goes out to contract too
In June 2026 Nama Water Services awarded a 15-year performance-based contract worth about RO 900 million to a SUEZ-led consortium for Muscat and North and South Al Sharqiyah, with pay tied to 33 KPIs. The handover date is still to be announced.
The state still stands behind it
These deals rest on a state-supported revenue base. Government subsidy made up 40.5% of Nama Water Services' 2024 operating revenue, and at the end of 2024 its current liabilities exceeded its current assets by RO 338 million. The utility had 97 projects worth around RO 966 million under execution in March 2026.
Which tenders close next, how the RO 11.1 billion master plan compares with the RO 666 million budget for 2025 to 2027, and what the risks mean for lenders, developers and contractors are set out in the brief. The full report, Water Infrastructure Investment and Project Pipeline in Oman, is available for USD 249. For a free overview, see https://ourfuturewaterintelligence.com/countries/oman.