Quotes for ion exchange resin for the Orange County Water District's PFAS treatment systems were due on November 3, 2026, under solicitation IFQ-26-001. No award had been published by November 18. The district's Board authorized a multi-year request for resin procurement, installation and disposal on August 19, 2026.
Plants in design
A centralized 16-vessel ion exchange plant for Santa Ana Wells 16, 29, 33 and 41 at the Walnut Pump Station moved forward when the district filed a CEQA exemption on September 17, 2026. An exemption for PFAS systems at Tustin's Edinger Well followed on October 22, 2026. Neither has a published construction award.
Still in procurement
The Board authorized a Notice Inviting Bids for Anaheim Wells 48 and 53 on June 17, 2026; no award has been announced. Santiago Pump Station modifications closed for bids on September 24, 2026.
Who pays
The district budgeted US$90.1 million for producer PFAS treatment facilities in FY2026-27, inside adopted expenditures of US$330.6 million. By June 2026 it had secured about US$283 million from grants, settlements and other sources, against projected PFAS costs of about US$1.8 billion over 30 years. An EPA grant of US$1,750,000 in May 2026 funds an innovative ion exchange system at Santa Ana Wells 27 and 28.
How to bid
Construction bids are advertised in The Orange County Register, documents sit in the district's Online Planroom, and contractors must be registered with the California Department of Industrial Relations. The Board awards to the lowest responsive bidder, as it did for Garden Grove after five bids in June 2026.
Who already holds the district's major work, how its finances stand and which opportunities rank highest for each supplier category are set out in the full brief. The full report, Orange County Water District: Utility Account Brief, is available for USD 499. For a free overview, read the Orange County Water District Utility Snapshot.