The San Diego County Water Authority runs 308 miles of large-diameter pipeline, 1,600 aqueduct-related structures and about 100 metering and flow control facilities, according to its 2024 Water Facilities Master Plan. Keeping that system working is the most consistent source of contract work at the agency.
Fifty miles relined so far
The Authority set up a formal Asset Management Program in June 2009. By March 2025 it had relined 50 miles of prestressed concrete cylinder pipe and rehabilitated 5 flow control facilities.
The current contract
Pipeline 5 Relining, from the Oceanside 5 Flow Control Facility to Huckleberry Lane in Bonsall, covers about 5,000 feet of pipe, a new isolation vault and structure upgrades. Work began in August 2026, with completion planned for summer 2027. ConstructConnect, a third-party bid service, reported the contract as awarded to James W. Fowler Co. for US$30,472,539.85 as of April 17, 2026.
The oldest aqueduct
A separate US$66 million project covers 99 structures on Pipelines 1 and 2 along the 21-mile Southern First Aqueduct. Pipeline 2 went back into service in February 2025 and Pipeline 1 work followed from March 2025, scheduled to finish in summer 2026.
Money is tight
The Authority's supplies fell from 488,618 acre-feet in FY 2016 to 291,721 in FY 2025. S&P cut its senior lien rating to AA from AAA on August 19, 2026, and the Board approved a 3% wholesale rate increase for 2027. Contractors should expect close scrutiny of price.
Which other projects are open or emerging, how the Authority buys through BidNet Direct and SCOOP, and where suppliers should focus first are set out in the full brief. The full report, San Diego County Water Authority: Utility Account Brief, is available for USD 499. For a free overview, read the San Diego County Water Authority Utility Snapshot.