01
Executive overview
Key findings
371 thousand tonnes: dry solids of sewage sludge produced in FY 2025/26, with 100% compliance with sludge regulations and codes of practice (actual)
About 49 Ml/d: demand savings in 2025-26 from household water efficiency (about 23 Ml/d), non-household water efficiency (more than 21 Ml/d) and smart meters (5 Ml/d), all ahead of plan forecasts (calculated from utility figures)
2031 to 2035: the risk Thames Water reports to the benefit date of the Teddington Direct River Abstraction, its first planned use of recycled effluent for supply (status)
15.1% against 21.3%: three-year average leakage reduction from the 2019/20 baseline, against the 2025/26 regulatory target (actual vs target)
02
Buyer relevance
Who the report is for
Sludge treatment, drying and thermal conversion providers
Assess a stream of 371 thousand tonnes of dry solids a year at sites that missed their Industrial Emissions Directive deadline, alongside two sludge super centres planned by 2030 and a pyrolysis demonstration.
Water recycling engineers and advanced treatment suppliers
Time engagement with Teddington (consent application early 2027, benefits 2031 at risk of 2035) and the 100–300 Ml/d Beckton options estimated for 2037–2039.
Metering, water efficiency and leakage firms
See which demand programs beat their forecasts in 2025-26 (about 23 Ml/d household and more than 21 Ml/d business savings) and where leakage remains short of target.
Regulators, lenders and policy advisers
Weigh circular commitments against the £20.5 billion PR24 allowance, the absence of a net zero allowance and the company's creditor funding position.
03
Decision scope
Questions answered
How much sewage sludge does Thames Water produce?
371 thousand tonnes of dry solids in FY 2025/26, with 100% compliance with sludge regulations and codes of practice.
Is Thames Water compliant with the Industrial Emissions Directive?
It did not complete the required works by the end of AMP7 in 2025; the Environment Agency has not accepted its original plan, and a New Directions Plan has been submitted.
When will London get recycled water?
The Teddington Direct River Abstraction, up to 75 million liters a day in dry weather, is forecast to deliver from 2031 with a risk of slipping to 2035; Beckton options of 100–300 Ml/d are estimated for 2037–2039.
How much water did demand programs save?
About 49 Ml/d in 2025-26 (calculated), from household efficiency (about 23 Ml/d), business efficiency (more than 21 Ml/d) and smart meters (5 Ml/d).
How much energy does Thames Water recover?
474.6 GWh of renewable energy produced and used on its own sites in FY 2025/26, 25.5% of its energy use.
04
Inside the report
Inside the complete report
Executive Overview at a Glance
1. Context and Baseline
2. Reduce
3. Reuse
4. Recycle
5. Recover
6. Policy and Governance
7. Implementation Achievements and Analytical Insights
8. Future Pathways
Conclusion
Source Register
05
Public preview
What to watch next
6. Policy and Governance
The Environment Agency's decision on the New Directions Plan; the October 29, 2026 creditor vote and any recapitalization decision; how the regulatory reforms following the Independent Water Commission treat sludge and resource recovery.
3. Reuse
The Teddington consent application and any revised cost and benefit date; Environment Agency agreement on the Mogden outfall; the Beckton Gate B investigations in 2026-27; approval of replacement membranes for Gateway.
2. Reduce
Leakage against the next annual target; mains replacement against the 110 km plan for 2026/27; demand savings during and after the 2026 Temporary Use Ban.
4. Recycle
The Environment Agency's response to the New Directions Plan; any change in land spreading rules; the reported share of sludge recycled to land in the FY 2026/27 regulatory tables.
Section 3: water recycling options and drought sources, with capacity and status at October 2026.

06
Included
What you receive
The complete PDF report: 12 pages, 11 sections, 13 tables and a register of 10 sources.
This edition
October 2026 edition. Covers FY 2025/26 (year ended March 31, 2026) and the first annual review of the Water Resources Management Plan 2024. Includes the overdue Industrial Emissions Directive works and the New Directions Plan submitted to the Environment Agency. Includes Teddington's benefit-date risk, the Beckton recycling investigations and the Gateway desalination outage. Includes the sludge pyrolysis demonstration, the two sludge super centres planned by 2030 and FY 2025/26 energy recovery. Time-sensitive facts checked to October 27, 2026. New edition, October 2026, with evidence current to 27 October 2026. Replaces the earlier edition for new buyers; buyers of an earlier edition keep access to the edition they bought.
07
Evidence & method
Evidence and method
The report draws on Thames Water's first Water Resources Management Plan annual review (2025-26), its FY 2025/26 annual report, annual performance report and sustainability and ESG statement, its leakage performance report, the Teddington project page, the PR24 final determination and current financing notices to October 2026.
Sources
10 sources, listed in the report's source register. Evidence current to 27 October 2026. Principal data periods: FY 2025/26 (year ended March 31, 2026) and the first annual review of the Water Resources Management Plan 2024 (2025-26); reuse, sludge and compliance status to October 2026. All currency is pounds sterling (£)..
Evidence boundaries
This report uses authoritative source material available at the stated research cutoff. It distinguishes published facts, calculated values and analytical interpretation. No independent modelling is performed. Forward-looking analysis reflects published plans, documented trends and stated uncertainties. It does not constitute legal, financial, investment or engineering advice.
08
Lead analyst
Robert C. Brears
Lead Analyst, Our Future Water Intelligence
Robert C. Brears is a water-security specialist and author whose work examines utility transformation, infrastructure, governance, finance and climate resilience for executive and policy audiences.
- Evidence-led water intelligence
- Decision-focused system analysis
- Report-specific treatment of scope and terminology
09
Buyer FAQs
Before you purchase
Who can use the report?
Licensed for internal use within one purchasing organization. The PDF and its contents may be shared with colleagues within that organization. External redistribution, resale and public publication are prohibited without permission.
How is the report delivered?
The PDF is available to download immediately after confirmed payment, through our secure delivery system.
Can my organization buy wider access?
Institutional purchasing: For invoice enquiries, multi-organization licensing or broader access requirements, contact Our Future Water Intelligence.
10
Circular Water Economy: Thames Water
- Format
- Length
- 12 pages
- Edition
- October 2026 edition
- Price
- USD 499
11
Report details
Publication details
- Publisher
- Our Future Water Intelligence
- Report family
- Water Utility Intelligence Report
- Report type
- Circular Water Economy
- Edition
- October 2026 edition
- Format
- Length
- 12 pages
- Reference
- OFW-8782321647794_1b768d7de6dd
- Evidence current to
- 27 October 2026
14
Explore this report family
More Circular Water Economy reports
Explore the same report family covering other utilities.

Circular Water Economy
Circular Water Economy: Berliner Wasserbetriebe
- Geography
- Berlin, Germany
- Edition
- 2026
- Length
- 21 pages

Circular Water Economy
Circular Water Economy: Anglian Water
- Geography
- East of England, United Kingdom
- Edition
- 2026
- Length
- 19 pages

Circular Water Economy
Circular Water Economy: PUB, Singapore's National Water Agency
- Geography
- Singapore, Asia
- Edition
- 2026
- Length
- 22 pages