01
Executive overview
Key findings
532 kWh/Ml and 252 kWh/Ml: net electricity used per megalitre of water supplied and of wastewater treated in FY 2025/26, against 525 and 254 in FY 2019/20 (actual)
£223.1 million: power costs in FY 2025/26 (FY 2024/25: £219.7 million), against £17.8 million of power income from selling self-generated electricity (actual)
£0: AMP8 (2025–2030) allowance for net zero schemes; the new operational emissions commitments were missed in FY 2025/26, with £4.07 million of penalties (actual)
132 GWh a year: onshore wind electricity contracted from RWE's Camster wind farm, December 2025 to 2030 (contract)
02
Buyer relevance
Who the report is for
Energy suppliers, power purchase agreement developers and solar installers
See how Thames Water buys power (132 GWh a year from RWE to 2030, forward contracts, the Little Marlow and Maidenhead PV tender) and where capital-light offers fit.
Providers of CHP maintenance, sludge treatment and low-carbon heat
Size the operating problem: CHP outages raised grid imports and boiler fuel use in FY 2025/26, and own generation fell to 20.2% of electricity.
Leakage, pumping and metering technology firms
Quantify the energy case for leakage reduction, with 573.7 Ml/d lost in FY 2025/26 equal to about 111 GWh of electricity a year at the company's average intensity.
Regulators, policy advisers and investors
Assess how a zero AMP8 net zero allowance, £4.07 million of emissions penalties and a creditor-funded capital program bear on Thames Water's energy plans.
03
Decision scope
Questions answered
How much energy does Thames Water use?
1,647 GWh in FY 2025/26, up 18 GWh on the year, of which electricity was 1,254.4 GWh.
Has Thames Water become more energy efficient?
Not for water supply: net electricity per megalitre of water was 532 kWh in FY 2025/26 against 525 kWh in FY 2019/20; wastewater moved from 254 to 252 kWh/Ml.
How much of its electricity does Thames Water generate itself?
20.2% in FY 2025/26 (253.3 GWh), down from 23.8% in FY 2021/22.
What does Thames Water spend on power?
£223.1 million in FY 2025/26 against £219.7 million a year earlier, with £17.8 million of power income from selling electricity produced on its own sites.
Is decarbonization funded in the 2025–2030 price control?
Thames Water received no AMP8 allowance for net zero schemes and incurred £4.07 million of penalties after missing its operational emissions commitments in FY 2025/26.
04
Inside the report
Inside the complete report
Executive Snapshot
1. Introduction
2. City Profile and Nexus Challenges
3. Operational Inefficiencies
4. Nexus Solutions and Opportunities
5. Financing and Partnerships
Future Outlook and Recommendations
Source Register
05
Public preview
What to watch next
5. Financing and Partnerships
The October 29, 2026 creditor vote and any recapitalization decision; whether AMP8 emissions penalties grow in FY 2026/27; how energy costs are treated in any revised regulatory settlement.
3. Operational Inefficiencies
CHP availability and emissions commitment results in the FY 2026/27 Annual Performance Report; net electricity intensity for water against 532 kWh/Ml; whether leakage falls toward its rising target.
4. Nexus Solutions and Opportunities
Award of the Little Marlow and Maidenhead PV contracts and the model chosen; progress toward the two sludge super centres planned by 2030; pyrolysis plant construction; CHP availability reported in FY 2026/27.
Future Outlook and Recommendations
Publication of the revised net zero goals; FY 2026/27 net electricity intensity and CHP availability; the outcome of the PV tender; any follow-on power purchase agreements as the RWE contract runs to 2030.
Section 3: energy intensity and electricity tables for FY 2019/20 and FY 2021/22 to FY 2025/26.

06
Included
What you receive
The complete PDF report: 12 pages, 8 sections, 11 tables and a register of 12 sources.
This edition
October 2026 edition. Covers FY 2025/26 (year ended March 31, 2026), the first year of the 2025–2030 price control, with energy comparisons to FY 2019/20. Includes the December 2025 RWE wind power purchase agreement, the 2026 Little Marlow and Maidenhead solar tender and the AMP8 electricity metering contract. Includes the zero AMP8 net zero allowance and the first-year results of the operational emissions commitments. Includes the 2026 Temporary Use Ban, Teddington's benefit-date risk and the October 2026 financing position. Time-sensitive facts checked to October 27, 2026. New edition, October 2026, with evidence current to 27 October 2026. Replaces the earlier edition for new buyers; buyers of an earlier edition keep access to the edition they bought.
07
Evidence & method
Evidence and method
The report draws on Thames Water's FY 2025/26 annual report, annual performance report and sustainability and ESG statement, compared with its 2019/20 combined report; its leakage performance report and net zero web page; the RWE power purchase agreement announcements; procurement notices for solar and electricity metering; and current project, drought and financing notices to October 2026.
Sources
12 sources, listed in the report's source register. Evidence current to 27 October 2026. Principal data periods: FY 2025/26 (year ended March 31, 2026), compared with FY 2019/20 and the five years to FY 2025/26; energy contracts, procurement and financing status to October 2026. All currency is pounds sterling (£)..
Evidence boundaries
This report uses authoritative source material available at the stated research cutoff. It distinguishes published facts, calculated values and analytical interpretation. No independent modelling is performed. Forward-looking analysis reflects published plans, documented trends and stated uncertainties. It does not constitute legal, financial, investment or engineering advice.
08
Lead analyst
Robert C. Brears
Lead Analyst, Our Future Water Intelligence
Robert C. Brears is a water-security specialist and author whose work examines utility transformation, infrastructure, governance, finance and climate resilience for executive and policy audiences.
- Evidence-led water intelligence
- Decision-focused system analysis
- Report-specific treatment of scope and terminology
09
Buyer FAQs
Before you purchase
Who can use the report?
Licensed for internal use within one purchasing organization. The PDF and its contents may be shared with colleagues within that organization. External redistribution, resale and public publication are prohibited without permission.
How is the report delivered?
The PDF is available to download immediately after confirmed payment, through our secure delivery system.
Can my organization buy wider access?
Institutional purchasing: For invoice enquiries, multi-organization licensing or broader access requirements, contact Our Future Water Intelligence.
10
Water-Energy Nexus: Thames Water
- Format
- Length
- 12 pages
- Edition
- October 2026 edition
- Price
- USD 499
11
Report details
Publication details
- Publisher
- Our Future Water Intelligence
- Report family
- Water Utility Intelligence Report
- Report type
- Water-Energy Nexus
- Edition
- October 2026 edition
- Format
- Length
- 12 pages
- Reference
- OFW-8782421491890_48c360cb5890
- Evidence current to
- 27 October 2026
14
Explore this report family
More Water-Energy Nexus reports
Explore the same report family covering other utilities.

Water-Energy Nexus
Water-Energy Nexus: Berliner Wasserbetriebe
- Geography
- Berlin, Germany
- Edition
- 2026
- Length
- 18 pages

Water-Energy Nexus
Water-Energy Nexus: PUB, Singapore's National Water Agency
- Geography
- Singapore, Asia
- Edition
- 2026
- Length
- 20 pages

Water-Energy Nexus
Water-Energy Nexus: SA Water
- Geography
- Australia, Oceania
- Edition
- 2026
- Length
- 21 pages