2,700 MW and 120 MIGD: Az-Zour North 2&3, under a 25-year energy conversion and water purchase agreement signed February 3, 2026; financial close pending
60 MIGD: Doha seawater reverse osmosis plant Phase 2, KD 114.28 million (about US$372 million) contract signed August 2026
17,540 MW: summer 2026 peak electrical load, about 70 MW below summer 2025 (minister's statement)
A1 / AA- / AA-: State of Kuwait sovereign ratings from Moody's, S&P and Fitch (2026); the ministry has no rating of its own
02
Buyer relevance
Who the report is for
Suppliers new to the Kuwaiti market
Get the ministry's mandate, procurement routes and live projects, from the US$316 million Doha complex to the about US$1.7 billion Subiya upgrade, in one reference.
Project developers and lenders
Check the status of Az-Zour North 2&3, Al-Khairan Phase 1 and Shagaya Phase 3 against the State of Kuwait's A1, AA- and AA- sovereign ratings.
Analysts and advisers
Use the side-by-side 2030 renewable goals, 15% of generation and 22,100 MW of capacity, and the tariff review timeline from May 12, 2025.
03
Decision scope
Questions answered
Is the ministry separately rated?
No. It is a government department; the State of Kuwait is rated A1 by Moody's and AA- by S&P and Fitch (2026).
Which projects are under contract?
Az-Zour North 2&3 (2,700 MW, 120 MIGD) under a 25-year agreement, Doha reverse osmosis Phase 2 (60 MIGD, KD 114.28 million) and the US$316 million Doha distribution complex.
What was the 2026 peak load?
17,540 MW in summer 2026, about 70 MW below summer 2025, according to the minister.
Have tariffs changed?
No tariff change had been adopted as of November 2026; a committee under Decision 103/2025 has been studying new tariffs since May 12, 2025.
04
Inside the report
Inside the complete report
Executive Overview
Utility and Service Mandate
Water Resources and Supply
Networks and Assets
Investment and Major Projects
Tariffs and Customer Context
Energy and Sustainability
Governance and Regulation
Climate and Resilience
Forward Developments
Key Intelligence Summary
Source Register
05
Public preview
What to watch next
Water Resources and Supply
A confirmed Al-Khairan Phase 1 capacity when a preferred bidder is named; start of works at Doha Phase 2.
Investment and Major Projects
Each of those three decisions, and whether any Subiya award differs materially from the reported values.
Tariffs and Customer Context
The committee's recommendations and any ministerial decision adopting them.
Governance and Regulation
The restructuring outcome; any change in sovereign outlooks.
Investment and Major Projects: every major contract, bid and plan with its value labelled as estimate, reported value or contract, and its status at November 2026.

06
Included
What you receive
The complete PDF report: 10 pages, 12 sections, 11 tables and a register of 21 sources.
This edition
November 2026, First edition.
07
Evidence & method
Evidence and method
The profile draws on Kuwait Authority for Partnership Projects records, International Energy Agency and World Bank policy and regional analysis, Central Bank of Kuwait copies of sovereign rating actions, ministerial statements, and trade-press reporting of 2026 contracts, bids and awards.
Sources
21 sources, listed in the report's source register. Evidence current to 10 November 2026. Principal data periods: Project, procurement, tariff and rating status from February to September 2026, checked against public sources on November 10, 2026; summer 2026 peak load; national targets for 2030. Currency is US dollars (US$) unless stated in Kuwaiti dinars (KD)..
Evidence boundaries
This report uses authoritative source material available at the stated research cutoff. It distinguishes published facts, calculated values and analytical interpretation. No independent modelling is performed. Forward-looking analysis reflects published plans, documented trends and stated uncertainties. It does not constitute legal, financial, investment or engineering advice.
08
Lead analyst
Robert C. Brears
Founder, Our Future Water Intelligence
Robert C. Brears is a water-security specialist and author whose work examines utility governance, infrastructure investment, climate resilience and long-term water-system change for executive and policy audiences.
- Decision-focused utility intelligence
- Published water-policy author
- Evidence-grounded system analysis
09
Buyer FAQs
Before you purchase
Who can use the report?
Licensed for internal use within one purchasing organization. The PDF and its contents may be shared with colleagues within that organization. External redistribution, resale and public publication are prohibited without permission.
How is the report delivered?
The PDF is available to download immediately after confirmed payment, through our secure delivery system.
Can my organization buy wider access?
Institutional purchasing: For invoice enquiries, multi-organization licensing or broader access requirements, contact Our Future Water Intelligence.
10
Utility Intelligence Profile: Ministry of Electricity Water and Renewable Energy
- Format
- Length
- 10 pages
- Edition
- November 2026, First edition
- Price
- USD 99
11
Report details
Publication details
- Publisher
- Our Future Water Intelligence
- Report family
- Utility Intelligence Profile
- Edition
- November 2026, First edition
- Format
- Length
- 10 pages
- Reference
- OFW_EXT_MINISTRY_OF_ELECTRICITY_WATER_AND_RENEWABLE_ENERGY_UTILITY_INTELLIGENCE_PROFILE_d017239ff6ee
- Evidence current to
- 10 November 2026
14
Explore this report family
More Utility Intelligence Profiles
Explore the same report family covering other utilities.

Utility Intelligence Profile: Aguas Andinas
- Geography
- Greater Santiago, Metropolitan Region, Chile
- Edition
- November 2026, corrected edition
- Length
- 11 pages

Utility Intelligence Profile: PUB, Singapore's National Water Agency
- Geography
- PUB, Singapore's National Water Agency
- Edition
- October 2026, First edition
- Length
- 13 pages

Utility Research and Reference
Utility Intelligence Profile: Denver Water
- Geography
- Denver metropolitan area, Colorado, United States
- Edition
- October 2026, updated edition
- Length
- 14 pages