Free Utility Snapshot

EYATH S.A.

Thessaloniki, Greece

State-controlled, listed water supply and sewerage company for greater Thessaloniki, stepping up investment under newly approved tariffs while cutting losses and emissions.

Paste the caption with your link. Social platforms control how previews appear.

At a glance

Scale, service and financial position

more than 1.2 millionCitizens served with water supply and sewerageCompany statement (undated)
26.84%Non-revenue water2025 · target: 50% reduction by 2030
around 522,261Water supply connectionsFY2025 annual report
60.5 million m³Wastewater treated annuallyAs stated in FY2025 annual report
€87,527 thousandTurnoverFY2025
€16,094 thousandEBITDAFY2025

01

About the Utility

EYATH provides water supply and sewerage services to more than 1.2 million citizens in the greater Thessaloniki Urban Area. Listed on the Athens Stock Exchange since 2001, it remains under state control: the Hellenic Republic holds 50% plus one share directly and a further stake through the Hellenic Republic Asset Development Fund. The company runs the urban water cycle from river, spring and groundwater sources through treatment and distribution to sewer collection and wastewater treatment. Its financial cost and tariffs are approved by the Regulatory Authority for Waste, Energy and Water. For the first regulatory period, covering 2025 to 2029, approved tariffs stay unchanged unless revised through an extraordinary review of financial cost.

02

Water System

EYATH draws on three sources: the Aliakmonas River, treated at the Thessaloniki Water Treatment Plant, the Aravissos springs in Pella, and boreholes in the plain of Thessaloniki. In 2025 the plant supplied 48,337,745 m³ of drinking water for consumption from Aliakmonas surface water. Supply reaches around 522,261 water connections, backed by reservoirs with 218,000 m³ of useful capacity. Losses remain a central operating issue: non-revenue water was 26.84% that year, against a target of halving it by 2030. EYATH is replacing older meters with volumetric and smart digital units, and its drinking-water laboratory is accredited.

48,337,745 m³Drinking water supplied for consumption from the Thessaloniki Water Treatment Plant2025
2,711.21 kmWater distribution networkFY2025 annual report
218,000 m³Total useful reservoir capacityFY2025 annual report

03

Wastewater System

EYATH also collects and treats the metropolitan area's wastewater. The Thessaloniki Wastewater Treatment Plant serves the central and western zones and is designed for 296,000 m³ a day, while the Aeneia plant, opened in 1997, serves eastern tourist areas. Together the plants treat 60.5 million m³ of wastewater a year. Thessaloniki's network includes combined sewers, and EYATH is working with Siemens on artificial intelligence and IoT tools to prevent overflows and floods. Treated water produced by the Sindos biological treatment station currently discharges to the Thermaikos Gulf.

1,724.38 kmSewerage networkFY2025 annual report
71,350Sewerage connectionsFY2025 annual report

04

Investment & Priorities

EYATH reports €14.3 million of investments completed in 2024, with further works contracts tendered or awarded. For 2025 to 2029, the regulator's decision records a submitted plan worth about €221.6 million, funded from EYATH's own and European funds and including 200,000 smart household meters. Named priorities include Phase A2 of the water treatment plant, completion of the sewerage network in Western Thessaloniki and repair of the Aravissos aqueduct. Implementation is drawing down cash, though the company operates with zero bank debt.

about €221.6 millionInvestment plan submitted for the regulatory period (plan)2025–2029
€48,819 thousandCash and cash equivalents31 December 2025
6.24%Approved return on capital employed (nominal pre-tax WACC)2025–2029 · EYATH sought 6.989%

Gross investment budget

Proposed annual budget for the 2025–2029 regulatory period, before grants

€ thousand
Gross investment budget: 2025, 37,792 € thousand, plan; 2026, 32,356 € thousand, plan; 2027, 46,420 € thousand, plan; 2028, 56,318 € thousand, plan; 2029, 48,727 € thousand, plan020,00040,00060,00037,792202532,356202646,420202756,318202848,7272029
Company plan

All five values are budget figures from one table in EYATH's March 2026 submission to the regulator (new works plus works in progress); none is an outturn. The regulator's decision records the submitted plan at about €221.6 million.

Sources: EYATH S.A., submission on the financial cost of the first regulatory period 2025–2029 (March 2026), total gross investment budget.

05

Sustainability & Resilience

Energy is central to EYATH's climate agenda. Total market-based emissions have fallen 47.21% from the base year, against a target of a 50% reduction by 2030. Unbundled energy attribute certificates now cover most market-based emissions from purchased electricity. For supply security, EYATH has stated that its main river source and the water table were at normal levels, and that supply would be fully covered through 2030 even in worst-case drought or infrastructure scenarios.

51,332.48 tCO₂eTotal emissions, market-based2025 · 47.21% below the 2022 base year
82,764.02 tCO₂eTotal emissions, location-based2025
80.08%Market-based purchased-electricity emissions covered by energy attribute certificates2025

06

Key Challenges

  1. Reducing non-revenue water from 26.84% in 2025 towards halving it by 2030.
  2. Delivering about €221.6 million of planned 2025–2029 investment under tariffs fixed for the period.
  3. Containing energy costs after electricity costs rose 78.72% in 2022 and EBITDA fell sharply.
  4. Expanding treatment capacity through Phase A2 of the Thessaloniki Water Treatment Plant.
  5. Managing overflow and flood risk on the combined sewer network.

07

Major Projects

Thessaloniki Water Treatment Plant, Phase A2

Expansion of the plant that treats Aliakmonas River water, supported by NSRF funding.

Status / period
Expected completion 2027 (April 2025 presentation)
Investment / capacity
€21.7 million plus VAT

Thessaloniki Wastewater Treatment Plant renovation

Renovation and energy improvement of the main plant serving the central and western zones.

Status / period
Scheduled for 2025 in the April 2025 presentation
Investment / capacity
€41m

Smart water meters

Meter modernisation, with 200,000 smart household meters in the 2025–2029 plan recorded by the regulator.

Status / period
Expected completion 2028 (April 2025 presentation)
Investment / capacity
€49.6m in the 2023–2028 plan

Evidence

Sources and reporting periods

This Snapshot draws on Our Future Water's governed evidence for EYATH: annual financial and sustainability reporting, investor presentations and company publications, together with EYATH's tariff submission and the Regulatory Authority for Waste, Energy and Water's decision for the first regulatory period.

Evidence through: 2026-09-2414 source documents

Report library

Reports on EYATH S.A.

5 reports available for purchase

Water Utility of the Future: EYATH S.A. cover

Utility transformation

Water Utility of the Future: EYATH S.A.

An assessment of how EYATH is turning from Thessaloniki's water and sewerage company into a regional system operator, and what its plans, regulation and funding allow it to deliver by 2030. EYATH has a regulator-approved €221.6 million investment plan for 2025-2029 and a legal deadline of July 31, 2027 to take over water supply, sewerage and irrigation across the Thessaloniki and Chalkidiki regional units. Delivering it means raising investment from €14.3 million completed in 2024 to about €44.3 million a year, with tariffs fixed to 2029 and a proposed EIB loan of about €150 million still under appraisal.
Edition
November 2026 edition
Price
USD 499
Explore report →
Water Systems Overview: EYATH S.A. cover

Water system overview

Water Systems Overview: EYATH S.A.

An overview of whether Thessaloniki's water system, from its river, springs and boreholes to its plants, networks and governing institutions, can absorb the expansion that EYATH takes on by July 2027. Thessaloniki's main source reaches the city through one treatment plant that averaged 93.2% of its first-phase capacity in 2025, while its second phase has slipped to 2027. The system is run by a debt-free, state-controlled company whose tariffs are now fixed to 2029 under a €221.6 million approved investment plan, and which must take over two regional units by July 31, 2027.
Edition
November 2026 edition
Price
USD 499
Explore report →
EYATH S.A.: Utility Account Brief cover

Utility account

EYATH S.A.: Utility Account Brief

A guide for suppliers to where EYATH spends, how it buys, who holds its major contracts and which Thessaloniki water and wastewater projects are open, confirmed or emerging. EYATH's regulator-approved €221.6 million plan for 2025-2029 averages €44.3 million a year, against €14.3 million of investment completed in 2024. In November 2026 it has open tenders for OT/SCADA telecommunications, server hardware and meter services, and it is preparing a new operation, maintenance and upgrade contract for its water treatment plant.
Edition
November 2026 edition
Price
USD 499
Explore report →

Explore the EYATH S.A. report collection

Stay informed

Our Future Water Intelligence updates

New analysis, water intelligence and report releases, delivered by email.