Water Utility IntelligenceSouth East Water Corporation

Free Utility Snapshot

South East Water Corporation

South-east Melbourne, Victoria, Australia

Retail water corporation serving about a third of Melbourne’s people, buying bulk water from a Melbourne system leaning on desalination, while dry-weather sewer spills rise.

Paste the caption with your link. Social platforms control how previews appear.

At a glance

Scale, service and financial position

1,831,777People serviced (783,591 residential and 63,231 business customers)FY2024-25 · actual
146 billion litresDrinking water suppliedFY2024-25 · actual
$329.3 millionCapital expenditureFY2024-25 · actual
$1,897.6 millionForecast capital expenditure adopted by the regulator2023–2028 price period · regulatory forecast
44Dry weather sewer spills (target 15)FY2024-25 · actual vs target
69.3%Melbourne water storage level1 September 2026 · status

01

About the Utility

South East Water Corporation is a Victorian water corporation providing water, sewerage and recycled water services across south-east Melbourne, home to about a third of the city’s population. Its latest annual report counts 1,831,777 people serviced, through 783,591 residential and 63,231 business customers. It operates as a retailer: Melbourne Water supplies its drinking water in bulk, and the Essential Services Commission sets its prices and monitors its service outcomes. The corporation pays dividends to its shareholder and borrows through the Treasury Corporation of Victoria under a government guarantee. Its customers pay the state’s lowest typical bill, yet the regulator attributes much of the sector’s recent rise in complaints to it and one other business.

02

Water System

The corporation buys its drinking water in bulk from Melbourne Water, so its supply security rests on the shared Melbourne system. That system is under strain. In 2024-25 total demand was the highest in decades while catchment inflows ran well below average, and the state has since ordered 150 billion litres from the Victorian Desalination Plant for 2026/27. In that peak-demand year the corporation supplied 146 billion litres of drinking water through 14,726 km of mains and maintained full compliance with drinking water quality standards, though a boil water advisory on the Mornington Peninsula and a Cranbourne complaint event tested operations.

169.6 billion litresWater supplied to South East Water by Melbourne Water2024/25 · actual (164.1 billion litres in 2023/24)
509 billion litresTotal demand on the Melbourne system, the highest since 1997/982024/25 · actual
150 billion litresWater ordered from the Victorian Desalination Plant2026/27 supply year · order, being delivered

03

Wastewater System

Sewerage is a core responsibility. In 2024-25 the corporation managed 148 billion litres of wastewater through 11,681 km of sewer pipes, and its eight water recycling plants also supply recycled water for non-drinking uses. Dry-weather sewer spills are its clearest performance gap. The regulator’s outcomes reports show them above the agreed target in each of the last two years, rising to 44 last year against a target of 15, and the corporation describes the latest result as well outside its annual target.

8.5 billion litresRecycled water suppliedFY2024-25 · actual
16, 24 and 44Dry weather sewer spills (targets 20, 15 and 15)FY2022-23 to FY2024-25 · actual vs target

04

Investment & Priorities

Capital spending has risen for three straight years, reaching $329.3 million in 2024-25, to support population growth and renew the water and sewer networks. For the current price period the regulator adopted a forecast capital programme slightly below the corporation’s proposal, shown side by side below, and its latest corporate plan proposes $2.2 billion for 2024–29. Digital metering is the largest project, expected to exceed $200 million, alongside a regional biofactory and the Fishermans Bend recycling plant. Gearing is forecast to rise in every year of the corporate plan.

$1.92 billionCapital programme proposed by the corporation (excludes works paid for by others)2023–28 · proposal (2023–28 Price Submission)
$2.2 billionProposed capital expenditure, nominal2024–29 · plan (Corporate Plan 2024–29)
54.4% to 61.8%Forecast gearing (total debt to total assets)FY2024-25 to FY2028-29 · forecast

Capital expenditure

South East Water Corporation, capital expenditure, $ million, financial years ending 30 June, 2019-20 to 2024-25

$ million
Capital expenditure: 2019-20, 260 $ million, actual; 2020-21, 257.9 $ million, actual; 2021-22, 171.7 $ million, actual; 2022-23, 217.1 $ million, actual; 2023-24, 301.1 $ million, actual; 2024-25, 329.3 $ million, actual01002003004002602019-20257.92020-21171.72021-22217.12022-23301.12023-24329.32024-25
Actual

Values as published in each year's annual report.

Sources: South East Water annual reports 2019-20 to 2024-25.

05

Sustainability & Resilience

Net emissions fell to 13,454 tonnes of carbon dioxide equivalent in the latest year, and the corporation reports sourcing all its electricity from renewables through generation and offsets, with net zero as a stretch target for 2028. It has linked longer supply interruptions to a few ageing assets, and in 2025 a Board of Inquiry found that a burst South East Water main caused the McCrae landslide; the corporation accepted all recommendations relating to it. Its drought plan relies on desalinated water to rebuild storage buffers.

13,454 t CO2-eNet greenhouse gas emissionsFY2024-25 · actual
Net zeroEmissions stretch targetBy 2028 · target
More than 7%Alternative water share of total water supplied (up from 4.5%)Corporate Strategy 2028 · target

06

Key Challenges

  1. Securing supply as the Melbourne system leans more heavily on desalinated water.
  2. Bringing dry-weather sewer spills back within the regulatory target.
  3. Funding a rising capital programme while gearing is forecast to climb.
  4. Restoring customer service standards as complaints and call waits increase.

07

Major Projects

Digital Metering project

The corporation's largest capital project for the current regulatory period.

Status / period
In the Corporate Plan 2024–29
Investment / capacity
Expected investment in excess of $200 million

South East Regional Biofactory – Stage 1

Regional biofactory project listed in the regulator's 2023–28 price determination.

Status / period
Listed in the 2023 determination with the years 2022-23 and 2032-33
Investment / capacity
Stage 1

Fishermans Bend Water Recycling Plant and Sewer Connection

Water recycling plant and sewer connection listed in the regulator's 2023–28 price determination.

Status / period
Listed in the 2023 determination with the years 2022-23 and 2029-30
Investment / capacity
Recycling plant and sewer connection

Evidence

Sources and reporting periods

This Snapshot draws on South East Water’s annual reports, drinking water quality reports, corporate plan and strategies, and on Essential Services Commission price decisions and performance reports and Melbourne’s annual water outlook and quarterly updates.

Evidence through: 2026-10-2321 source documents

Report library

Reports on South East Water Corporation

0 reports available for purchase

No reports are currently available for purchase.

Stay informed

Our Future Water Intelligence updates

New analysis, water intelligence and report releases, delivered by email.