Free Utility Snapshot

Uisce Éireann

Republic of Ireland (national public water and wastewater services)

Ireland’s national public water utility, State-funded and independently regulated, investing to close supply deficits, cut leakage and complete wastewater compliance.

Paste the caption with your link. Social platforms control how previews appear.

At a glance

Scale, service and financial position

€1,431mCapital investment2025 · actual
€1,837mRevenue (of which Government subvention €1,243m)2025 · actual
1,780 Ml/dDistribution input (water put into supply)2024 · actual, as resubmitted to the regulator
35.8%National leakage rate2025 (12-month rolling average to 30 September) · actual
over 99.8%Public water supplies complying with bacterial and chemical limits2024 · actual (EPA)
93%Agglomerations compliant with the Urban Waste Water Treatment Directive2025 · actual

01

About the Utility

Uisce Éireann is Ireland’s national water services authority. It took over statutory responsibility for public water services in 2014, replacing local authorities as water services authorities, and later became a standalone public authority separate from its former parent, Ervia. It supplies drinking water to over 80% of the population and wastewater services to about 66% of households, serving more than 1.8 million customers. Domestic customers do not pay water charges directly: the State pays on their behalf, and most funding comes from the Exchequer. The Commission for Regulation of Utilities sets its allowed revenue and performance targets, and the transfer of remaining local authority responsibilities is due to be completed by 2026.

02

Water System

Most public supplies are drawn from surface water, and the Liffey provides 85% of supply to 1.7 million people in the Eastern and Midlands region. Demand is outgrowing available water: distribution input rose to 1,780 Ml a day in 2024, when most of the population was served by water resource zones in deficit. Leakage is the main lever: the national rate has fallen from a peak of 46% to 35.8% in 2025, but the leakage target of the last price control was missed and penalised. Drinking water quality is high, and boil water notices now affect far fewer people.

84–87%Share of the population served by a water resource zone in deficit2024 · as reported by Uisce Éireann
35Public supplies on the EPA Remedial Action List (45 at the start of the year)End of 2025 · actual
25%National leakage rate targetBy end of 2030 · target

Distribution input

Uisce Éireann, distribution input (water put into supply), million litres a day, calendar years 2016 to 2024

Ml/d
Distribution input: 2016, 1,657 Ml/d, actual; 2017, 1,673 Ml/d, actual; 2018, 1,701 Ml/d, actual; 2019, 1,693 Ml/d, actual; 2020, 1,667 Ml/d, actual; 2021, 1,663 Ml/d, actual; 2022, 1,683 Ml/d, actual; 2023, 1,730 Ml/d, actual; 2024, 1,780 Ml/d, actual1,6001,6501,7001,7501,8001,8501,65720161,67320171,70120181,69320191,66720201,66320211,68320221,73020231,7802024
Actual

Figures as resubmitted by Uisce Éireann to the regulator; 2019 is the baseline year of the 2020–2024 price control.

Sources: Commission for Regulation of Utilities, RC4 Final Determination Paper (May 2026).

03

Wastewater System

Uisce Éireann collects and treats more than 1.2 billion litres of wastewater a day through over a thousand treatment plants and a national sewer network. Compliance is improving from a low base: 93% of agglomerations met the Urban Waste Water Treatment Directive in 2025, but on provisional figures only 53% of the population equivalent did. Places with no or only preliminary treatment fell to 16 by 2024. The upgraded Ringsend plant, Ireland’s largest, was completed in February, while the European Commission has asked the EU Court of Justice to fine Ireland over agglomerations still in breach of an earlier judgment.

53%Population equivalent served by compliant agglomerations (provisional)2025 · actual, provisional
16Agglomerations with no or only preliminary treatment (34 in 2020)2024 · actual

04

Investment & Priorities

Capital investment reached €1,431m in 2025, supported by Government capital contributions. For the five years to 2029, the regulator allows €13.6bn of expenditure, including €8.56bn of capital spending and a €1.4bn leakage plan; these are allowances, not outturns. The largest planned scheme, the Water Supply Project from the Shannon to Dublin, awaits a planning decision now expected by July 2027; Greater Dublin Drainage has moved into procurement, and extra Government funding for housing growth is being added to the plan.

€13.6bnAllowed expenditure (€8.56bn capital, €5.06bn operating)2025–2029 · regulatory allowance (2022 prices)
€1.4bnLeakage plan expenditure allowed2025–2029 · allowance
30 MLDMinimum net leakage reduction requiredBy end of 2029 · target

05

Sustainability & Resilience

Uisce Éireann aims for net zero by 2040, ahead of the semi-state sector’s 2050 deadline, and now publishes a verified greenhouse gas footprint. Energy is a major driver, as water and wastewater services need more than a thousand gigawatt hours a year. Resilience is the sharper test: the national resources plan showed demand exceeding available water in every weather scenario, and dry weather this year brought a national hosepipe ban, lifted early in September.

807,669.19 tonnesGreenhouse gas emissions, carbon dioxide equivalent, verified, location-based (market-based 865,824.76)2024 · actual
550 Ml/dLargest national supply deficit (dry-year critical period)Base year 2019 · planning assessment
2040Net zero ambitionTarget

06

Key Challenges

  1. Closing supply deficits across Dublin and the Eastern and Midlands region.
  2. Delivering the Water Supply Project through planning, procurement and construction.
  3. Reducing leakage towards the national target of 25% by 2030.
  4. Bringing the remaining agglomerations into wastewater compliance.
  5. Funding a much larger capital programme that relies on the Exchequer.

07

Major Projects

Water Supply Project – Eastern and Midlands Region

Planned new supply from the River Shannon to the Dublin area, reducing reliance on the Liffey.

Status / period
Planning application with An Coimisiún Pleanála; decision expected by July 2027
Investment / capacity
Serves a region where 85% of supply to 1.7 million people comes from the Liffey

Greater Dublin Drainage

Planned regional wastewater scheme for the Greater Dublin Area, adding treatment capacity for growth.

Status / period
Procurement; main contract award expected 2028 (as reported)
Investment / capacity
Regional wastewater treatment and sewer scheme

National Leakage Reduction Programme

Ongoing national programme of mains repair, renewal and leak detection, including the First Fix scheme.

Status / period
In delivery; 25% national leakage target for 2030
Investment / capacity
€1.4bn allowed for 2025–2029; minimum 30 MLD net saving

Evidence

Sources and reporting periods

This Snapshot draws on Uisce Éireann’s annual reports for 2016 to 2025, the regulator’s revenue control decisions, performance and customer reports, government water services policy statements, and the utility’s resources, funding and strategic plans.

Evidence through: 2026-10-1620 source documents

Report library

Reports on Uisce Éireann

0 reports available for purchase

No reports are currently available for purchase.

Stay informed

Our Future Water Intelligence updates

New analysis, water intelligence and report releases, delivered by email.