01
About the Utility
Unitywater, formally the Northern SEQ Distributor-Retailer Authority, is a statutory body created in the 2010 restructuring of South East Queensland’s water sector. Its participants are the Moreton Bay, Sunshine Coast and Noosa councils, which hold its subordinated debt and receive tax equivalents, interest and dividends from it. As the region’s distributor-retailer it buys treated bulk water from Seqwater, runs the local water and wastewater networks and bills households and businesses directly. Unitywater sets its own prices, which the Queensland Competition Authority monitors without setting; its current review runs to 2030. For 2026-27 the utility held water charges flat, so the average combined bill rose 1.6%, from wastewater charges only.
02
Water System
Unitywater buys treated bulk water from Seqwater and distributes it through a network of mains, reservoirs and pump stations. The cost of those bulk purchases has kept rising, making Seqwater’s charges a large share of what customers pay. The network performs well against national peers: water main breaks ran at 3.5 per 100 kilometres in 2024-25, against an industry figure of 16.8, and drinking water has met quality requirements in full. Leakage is the weak point: real losses of 55 litres per connection a day remain above the utility’s own Customer Charter target of 45, and digital metering is still a regional pilot.
Drinking water supplied
Unitywater, drinking water supplied, megalitres a year, financial years ending 30 June, 2018-19 to 2025-26
Values as published in each year's annual report (2018-19 is the report's infographic value).
Sources: Unitywater annual reports 2018-19 to 2025-26.03
Wastewater System
Wastewater is a core responsibility. Unitywater collects sewage through its own mains and pump stations and treats it at 17 plants, returning part of the flow as recycled water, including Class A water supplied to farmers through the Wamuran Irrigation Scheme. Sewer breaks and chokes ran at 4.3 per hundred kilometres in 2024-25, against 26.9 across major utilities. Growth pressure is concentrated here: the Burpengary East plant upgrade, the largest single item in its latest trunk-infrastructure register, is under construction for completion in early 2027, and a redesign of the Brendale plant cut its estimated cost by tens of millions of dollars.
04
Investment & Priorities
Unitywater invested $386 million in growth and renewal in 2025-26, and its strategy commits to $2 billion of new and renewed infrastructure by 2030, delivered through long-term partnership contracts. For the three years to 2030 it proposes a further $1.6 billion, led by major wastewater growth projects. Borrowing is rising with the programme, and Queensland Treasury Corporation’s latest credit review found debt serviceability and leverage outside its preferred benchmark range, though comparable to peers and within lending covenants.
05
Sustainability & Resilience
Resilience planning centres on growth and climate. The strategy expects 520,000 more people across the region over the next two decades, and the recycled water strategy cites modelling of more frequent and longer droughts. Unitywater targets net zero emissions by 2040 and a ‘Net Positive Blue’ position that maximises recycled water use and cuts nutrient discharges to waterways. In 2025-26 it reported lower carbon emissions alongside its own renewable energy generation.
06
Key Challenges
- Delivering a wastewater-led capital programme as the region adds hundreds of thousands of residents.
- Maintaining financial headroom as borrowing sits outside Queensland Treasury Corporation’s preferred benchmarks.
- Reducing real water losses to the utility’s own Customer Charter target.
- Renewing ageing asbestos-cement water mains over the coming decades.
- Keeping bills affordable through the Queensland Competition Authority’s 2026-30 review.
07
Major Projects
Burpengary East wastewater treatment plant upgrade
Capacity upgrade at Uhlmann Road, the largest single trunk-infrastructure item in 2024-25.
- Status / period
- Under construction (completion expected early 2027)
- Investment / capacity
- $54,824,386 spent in FY2024-25
Tanawha and Landsborough reservoirs
Two new drinking water reservoirs for growth areas on the Sunshine Coast, with new water mains.
- Status / period
- Under construction (December 2025 report)
- Investment / capacity
- Tanawha: 12 ML reservoir and 500 mm main
Wamuran Irrigation Scheme
Class A recycled water from South Caboolture piped to Wamuran farmers, reducing discharges to the Caboolture River.
- Status / period
- Operating
- Investment / capacity
- Designed for 2.6 GL a year