Amsterdam's 3,900 km Sewer Network Needs About 65 km of Renewal a Year

Amsterdam's sewer program (2022–2027) puts the network at about 3,900 km needing about 65 km of renewal a year; of 40 km planned in a year, fewer than 30 km may be replaced.

Amsterdam's sewer program for 2022–2027 puts the city's network at about 3,900 km, with an average service life of about 60 years. That means roughly 65 km of sewer needs replacing every year, and the program's own figures show delivery falling short of plan.

Plans versus pipes in the ground

The program planned 48 km of replacement a year in 2022 and 2023, rising to about 66 km a year after that, including 5 km for Weesp. It also states that of 40 km planned at the start of a year, fewer than 30 km may actually be replaced. At that rate, delivery would fall below three-quarters of the year's plan.

What the network holds

The inventory is large: 2,242 km of foul-water sewers, 1,674 km of stormwater sewers, 1,165 sewage pumping stations, 43 storage-settling facilities and 338 external overflows. Waternet manages it for the City of Amsterdam.

A failure in Amsterdam-Noord

On August 30, 2026 a large sewer main failed at the Zuiderzeeweg in Amsterdam-Noord. Sewage and rainwater flowed into local watercourses, and fish died; the water authority Hoogheemraadschap Hollands Noorderkwartier took measures in the affected water. Waternet's update of November 3, 2026 says the main is back in use.

Who renews the next 65 km

The 2022–2027 program ends next year. Under the second phase of Waternet's split, which took effect in its first phase on January 1, 2026, Amsterdam's sewer and water-management tasks are due to return to the city, with no date set.

Which body commissions the successor program, how the sewer task compares with the pressures on Amsterdam's drinking water supply, and what the city's new institutional map means for incident response are among the questions the report answers. The full report, Water Systems Overview: Waternet, is available for USD 499. For a free overview, read the Waternet Utility Snapshot.

Continue reading

Related News

AnalysisWaternet's January 2026 Split Moved 12 Treatment Plants' Worth of Work to the Water Board

Waternet split on January 1, 2026; the 12 treatment plants it ran for AGV in 2015 left with the water board, while it keeps a 3,355 km drinking water network.