Austin's 2024 Drought Contingency Plan puts the city's five-year average diversion at about 164,409 acre-feet a year, about half of its firm Colorado River and Highland Lakes supply of 325,000 acre-feet. The harder question is time: the largest new supply in its 2040 plan has not yet left the field-testing stage.
Headroom today, a long plan ahead
The utility's medium projection puts diversions at 183,000 acre-feet in 2040, still 56.3% of firm supply. But Austin draws its drinking water from one river system, and the Water Forward 2024 plan models more than 600 futures. Without new strategies, 37% of them show a need of 100,000 to 300,000 acre-feet a year by 2070. With the strategies in place, fewer than 3% show a shortage through 2060.
The aquifer timeline
Those strategies total 90,100 acre-feet a year in 2040, and aquifer storage and recovery accounts for 44,500 of them in the 2024 plan. In November 2025 Austin dropped its Bastrop County test site and moved field testing to City-owned land in eastern Travis County. Test wells follow from spring 2027 and a Phase 1B report in spring 2028. A pilot of about 36 months and eight to ten years of full-scale design and construction come after that.
A contract threshold in the background
Austin's 1999 agreement with the Lower Colorado River Authority, prepaid at US$100 million, triggers payments when two-year average use exceeds 201,000 acre-feet a year. Austin Water credits conservation with delaying that point by up to eight years. Per-capita use fell from more than 160 gallons a day in 2011 to about 131 in 2023.
What would a delay in the aquifer program mean for the 2040 portfolio, how do reuse and loss control fill the gap, and who decides each step? The full report, Water Systems Overview: Austin Water, is available for USD 499. For a free overview, read the Austin Water Utility Snapshot.