Bahrain Retenders Its First Solar IPP and Moves Target Operation to End-2028

Bahrain retendered its 100 MW Bilaj Al Jazayer Solar IPP on 8 November 2026, moving target operation to 31 December 2028; renewables were 1.26% of capacity in 2022.

Paste the caption with your link. Social platforms control how previews appear.

Bahrain's Electricity and Water Authority (EWA) issued a new tender for the 100 MW Bilaj Al Jazayer Solar IPP on 8 November 2026, with a target commercial operation date of 31 December 2028. The earlier round had aimed for 30 September 2027, so the first utility-scale solar IPP in the Kingdom is now due more than a year later.

An earlier round with a clear low bid

In the earlier round, Yellow Door Energy was reported lowest at BHD11.398m against ACWA Power's BHD15.440m in June 2026. The new tender, 538/2026/BTB, keeps the build-own-operate model and asks for bids by 20 December 2026. The notice gives no reason for the new round and names no developer.

Utility-scale solar trails rooftop growth

EWA's own 100 MW plant at Al Dur had a completion target of the third quarter of 2026, and it has not yet been announced as complete. Distributed solar has moved faster. Net-metering capacity rose from 15.2 MW in 2023 to more than 43.4 MW in 2025, and 372 renewable projects above 141 MW were producing over 230 GWh a year by June 2026.

The 2035 gap

Renewables made up 1.26% of Bahrain's installed capacity in 2022, against a national target of 20% by 2035. The pace matters for water too: 89% of Bahrain's water-related electricity went to desalination in 2017.

How EWA is moving from plant owner to buyer of private supply, what its loss and storage commitments add up to, and which awards fall due before 2030 are set out in the report. The full report, Water Utility of the Future: Electricity and Water Authority, is available for USD 499. For a free overview, read the Electricity and Water Authority Utility Snapshot.

Continue reading

Related News

AnalysisBahrain's Water Storage Has Grown by Nearly Half Since 2015

EWA's water storage reached 722 million imperial gallons in 171 tanks in 2024, up 48.3% from 2015 and about 4.3 days of average production.

View all News →

Stay informed

Our Future Water Intelligence updates

New analysis, water intelligence and report releases, delivered by email.