The Electricity and Water Authority (EWA) held 722 million imperial gallons of water storage across 171 tanks in 2024, up from 487 million imperial gallons in 130 tanks in 2015. That is a rise of 48.3%, and in 2024 it equaled about 4.3 days of average production of 168.89 MIGD.
Storage for a desalinated system
Desalinated water made up 100.0% of Bahrain's production in 2020–2022, and installed production capacity stood at 213.22 MIGD in 2024. With supply drawn from plants rather than rainfall, storage is what carries the system through a plant outage.
More transfer capacity financed
A US$407 million second phase of Al Dur water transmission and storage, approved in September 2022, is designed to raise transfers from Al Dur from 744,000 to 971,000 m³ a day for demand to 2030. Development lenders provide US$270.21 million of it: the Islamic Development Bank US$80 million, the Saudi Fund US$95 million and the Abu Dhabi Fund for Development US$95.21 million.
New plants behind the tanks
Two private reverse osmosis plants are in procurement. Hidd, at 60 MIGD, is expected by MEED to be fully operational by 2029; Sitra, at 30 MIGD, has an award expected by the end of 2026. The distribution network is being renewed as well: the aged share of mains fell from 25.1% in 2023 to 23.4% in 2024, while mains grew from 2,935 km to 3,007 km.
How EWA is moving from plant owner to buyer of private supply, what its 23% loss target for 2032 depends on, and which awards fall due before 2030 are set out in the report. The full report, Water Utility of the Future: Electricity and Water Authority, is available for USD 499. For a free overview, read the Electricity and Water Authority Utility Snapshot.