Cape Town now expects to finish its committed New Water Programme, a peak design capacity of 305 Ml/day, by December 2036. The 2019 Water Strategy aimed for more than 300 Ml/day within ten years, and the June 2025 Water Outlook still projected December 2031.
Reuse moves first
The first large advanced-treatment scheme is now in procurement. On 25 September 2026 the City opened the qualification stage for the Faure New Water Scheme, a public-private partnership that Council backed in principle in December 2025. Proposals are scheduled for the second half of 2027, and Phase 1 is planned to deliver 70 Ml/day of purified recycled water by June 2031.
Desalination slips
Desalination Phase 1, also 70 Ml/day, is now dated December 2036. Council chose a public-private partnership for a plant at Paarden Eiland in December 2025, but the port authority's revised planning led the City to start looking at other sites. Separately, the national Berg River Voëlvlei Augmentation Scheme, worth 40 Ml/day to the City, is now dated May or June 2030.
The squeeze before then
The City expects to reach its raw water allocation from the Western Cape Water Supply System within the next two years. Groundwater is helping: the Table Mountain Group wellfield and the Atlantis scheme are producing, and the 6 Ml/day Strandfontein West plant is being commissioned. Cost is the other pressure. The City puts current bulk water at R7.38/m3 and New Water Programme water at about R18/m3 in 2025 rand.
Which schemes carry the gap to 2036, how the City's climate planning assumptions changed in June 2026, and what more than R10 billion of bulk infrastructure work implies are covered in the full report. The full report, Water Utility of the Future: Water and Sanitation Directorate, City of Cape Town, is available for USD 499. For a free overview, read the Water and Sanitation Directorate, City of Cape Town Utility Snapshot at https://ourfuturewaterintelligence.com/utilities/water-and-sanitation-directorate-city-of-cape-town.