Doha South Sewage Plant Is 65% Built, and Its Twin PPP Raises a Question

Ashghal's QR 6.3bn Doha South sewage plant was 65% complete in November 2026 and is due in Q2 2028, with 150,000 m³ a day for more than 300,000 people.

Paste the caption with your link. Social platforms control how previews appear.

Ashghal's new Doha South Sewage Treatment Plant was about 65% complete in mid-November 2026, with its first phase due in the second quarter of 2028, according to the Qatar News Agency on 16 November.

Scale and finance

The first phase will treat 150,000 m³ a day and serve more than 300,000 people in southern Qatar, with room to expand to 600,000 m³ a day. It is a 25-year public-private partnership with a total investment of QR 6.3bn, including about QR 2.3bn of foreign investment. Al Attiyah is the largest shareholder in the consortium.

A familiar profile

Those numbers closely match the Al Wakrah and Al Wukair Sewage Treatment Works, a PPP signed on 4 September 2022: 150,000 m³ a day initially, expandable to 600,000, for more than 306,000 people, at more than QAR 5.4bn over 25 years. That project was due in 2026 and was last reported under construction in January 2025. Neither source says the two are one project, and the totals differ.

Why it matters for reuse

Qatar treated 99.7% of its sewage in 2021, and Ashghal targets reuse of 100% of treated wastewater by 2030. The new plant is planned to produce biogas from sludge for its own power and heat; the national emissions inventory for 2019–2023 states that on-site biogas production at treatment plants "does not occur".

Whether the two PPPs are one asset, where the D-Line effluent main and storage lagoons stand, and how Doha's water and wastewater investment adds up are examined in the full report. The full report, Doha Water Intelligence Report, is available for USD 799. For a free overview, see Doha City Snapshot.

Continue reading

Related News

AnalysisPhysical Losses on the Network Serving Doha Rose From 3.97% to 5.71%

Real water losses on Qatar's national network, which serves Doha, rose from 3.97% in 2019 to 5.71% in 2023, as KAHRAMAA added about 298,000 smart water meters in 2025.

View all News →

Stay informed

Our Future Water Intelligence updates

New analysis, water intelligence and report releases, delivered by email.