Analysis

Physical Losses on the Network Serving Doha Rose From 3.97% to 5.71%

Real water losses on Qatar's national network, which serves Doha, rose from 3.97% in 2019 to 5.71% in 2023, as KAHRAMAA added about 298,000 smart water meters in 2025.

Paste the caption with your link. Social platforms control how previews appear.

Physical water losses on the national network that supplies Doha rose from 3.97% in 2019 to 5.71% in 2023, according to KAHRAMAA's Annual Statistics Report 2023. Losses peaked at 6.18% in 2021 and have eased only slightly since.

A small share of a large volume

The percentages look modest, but they apply to a national system that produced 666 Mm³ of water in 2025, almost all of it desalinated seawater. KAHRAMAA runs one network of over 11,000 km for the whole country, so Doha's losses cannot be separated from Qatar's.

Two measures, not one trend

In its review of 2025, KAHRAMAA reported "technical water losses" below 4.5% and called the figure among the best international benchmarks. That is a different measure from the real losses in the 2023 report, and neither is a non-revenue water rate, which would also count meter errors and unbilled use.

Meters first

KAHRAMAA's response so far has been metering and data. It added about 298,000 residential water meters to its advanced metering system in 2025 and reported water billing accuracy of 97.74%. A customer data project completed in October 2025 updated more than 900,000 reading meters. The utility also brought 23.7 km of new water lines into operation in 2025.

The money behind it

KAHRAMAA's 2026–2030 project plan, presented in December 2025, puts water projects at about QAR 4.1bn, without a published project list or a stated share for loss reduction.

Whether metering is enough to bring losses back toward 2019 levels, how Doha's supply concentration and storage compare with its demand, and where Ashghal's wastewater and reuse works stand are examined in the full report. The full report, Doha Water Intelligence Report, is available for USD 799. For a free overview, see Doha City Snapshot.

Continue reading

Related News

AnalysisDoha South Sewage Plant Is 65% Built, and Its Twin PPP Raises a Question

Ashghal's QR 6.3bn Doha South sewage plant was 65% complete in November 2026 and is due in Q2 2028, with 150,000 m³ a day for more than 300,000 people.