The Mayor's proposed 2027–2032 capital program for Seattle Public Utilities' drainage and wastewater system totals US$2,344.3 million, up from US$2,181.9 million in the adopted 2026–2031 program. The Council had not adopted the proposal by November 16, 2026.
Overflow deadlines
Under the May 2025 modification of the combined sewer overflow Consent Decree, all overflow construction is due by December 2037 and control by 2038. About US$428 million of overflow reduction is planned for 2026–2031. The Ship Canal Water Quality Project, shared with King County, has a total project cost of about US$710 million; the proposed CIP funding table totals US$760.8 million. Its tunnel is expected to operate in 2027.
Sediment cleanup
EPA estimates the Lower Duwamish Waterway cleanup at US$668 million. A proposed consent decree was lodged in March 2026, with court approval not reported by November 16, 2026. The proposed CIP gives Seattle Public Utilities' Sediment Remediation program a total of US$644.4 million including life-to-date and 2026 (about US$525 million in 2027–2032); about 64% of Sediments costs are expected to be reimbursed. SPU's May 2026 contract list includes a US$200 million Middle Reach construction contract for Q4 2027.
Drainage in the Duwamish Valley
The South Park and Duwamish Valley Integrated Projects carry a total project cost of US$134.9 million, with a pump station in construction and a water quality facility in design.
Paying for it
The Drainage and Wastewater Fund reported operating revenues of US$610.8 million in FY 2025 and had US$980.8 million of parity bonds outstanding at the end of 2025, including a US$192.2 million WIFIA loan at a fixed 1.01%. Moody's rates the system Aa1 with a positive outlook.
How suppliers can reach this work, which contracts are already held and what to watch through 2027 are covered in the brief. The full report, Seattle Public Utilities: Utility Account Brief, is available for USD 499. For a free overview, read the Seattle Public Utilities Utility Snapshot.