Thames Water awarded its AMP8/9 Major Projects Framework to nine contractor teams, with the award notice published on 23 October 2026. The framework is estimated at £4 billion excluding VAT, or £4.8 billion including VAT, but a place on it guarantees no volume of work.
Who is on it
The nine teams are Ferrovial Construction (UK) with Cadagua and Binnies; Taylor Woodrow with Amentum; BAM Nuttall; Barhale; Costain; J. Murphy & Sons; Galliford Try; Kier Infrastructure and Overseas; and Mott MacDonald Bentley. The initial term runs to 31 March 2030 and can be extended to 31 March 2035.
What comes first
The first wave is worth £840 million and covers 10 projects, including Crossness and Didcot sewage treatment works. That fits the spending pattern: pollution prevention took £996 million of Thames Water's capital investment in FY 2025/26, the largest of its four investment themes.
Why the work is needed
Discharge permit compliance fell to 88.22% in FY 2025/26, from 98.7% a year earlier, which the company attributes to tighter permit limits. The August 2026 delivery plan lists 14 critical schemes, and some are slipping: contract awards at Maple Lodge and Harpenden moved back a quarter, and Bracknell is forecast for March 2033.
The counterparty question
The framework sits inside a company that had drawn £2.65 billion of a £3 billion creditor facility by 15 October 2026. A court sanction hearing on 13 January 2027 decides whether 2027 debt maturities move to March 2028.
Which other contracts are open, how Thames Water buys outside the frameworks and where suppliers should focus first are set out in the full brief. The full report, Thames Water: Utility Account Brief, is available for USD 499. For a free overview, read the Thames Water Utility Snapshot.