Thessaloniki's Treatment Plant Ran at 93.2% of Its First-Phase Capacity in 2025

Thessaloniki's water treatment plant averaged about 139,752 m3 a day in 2025, 93.2% of its 150,000 m3/day first phase; the second phase is now due in 2027.

Paste the caption with your link. Social platforms control how previews appear.

The Thessaloniki Water Treatment Plant treated 51,009,656 m3 of Aliakmonas River water in 2025, an average of about 139,752 m3 a day. That is 93.2% of the 150,000 m3/day capacity of the plant's first phase, which has operated since August 2003.

The second phase has slipped to 2027

EYATH's €21.7 million second phase would raise capacity to 300,000 m3/day. It was under construction at June 30, 2026, with completion last stated for 2027 after slipping from early 2025. The company's FY2025 annual report already describes a 300,000 m3/day plant "following expansion", but that is the design figure, not operating capacity.

Output is steady

Average daily supply from the plant was 133,642 m3 in 2024, 132,381 m3 in 2025 and 128,222 m3 in H1 2026. Total consumption across EYATH's system was 56.2 million m3 in 2024, two-thirds of it by households. Non-revenue water stood at 26.84% in 2025, and EYATH targets a 50% reduction by 2030.

Backup sources and new studies

The Aravissos springs and boreholes in the Thessaloniki plain back up the river. EYATH signed a third framework of €9 million in June 2026 to keep strengthening the Aravissos aqueduct, and in the same month contracted a €144,537.75 climate resilience report. A €250,619.04 catchment risk assessment for its abstraction points was at the call stage at the H1 2026 report.

How the system's governance is changing under Law 5325/2026, what the €221.6 million approved investment plan covers, and which works and studies come next are set out in the report. The full report, Water Systems Overview: EYATH S.A., is available for USD 499. For a free overview, read the EYATH S.A. Utility Snapshot.

Continue reading

Related News

AnalysisA New Law Gives EYATH Two Regional Units by July 2027

Law 5325/2026 gives EYATH until July 31, 2027 to take over water, sewerage and irrigation across Thessaloniki and Chalkidiki; shareholders vote on November 20, 2026.

View all News →

Stay informed

Our Future Water Intelligence updates

New analysis, water intelligence and report releases, delivered by email.