Watercare's Huia Water Treatment Plant, built in 1928, treats about 20% of Auckland's water. Its replacement, consented in December 2023 for up to 160 ML/d, has been rephased: major construction funding is now forecast from 2033, the project runs to 2038, and no construction contract has been awarded.
A program stretched past its dates
Huia is one of seven projects in the Western Water Supply Programme, which Watercare values at over NZ$1 billion and lists for 2025–2034. Other parts are moving: construction of the May Road booster pump station began in April 2026 and is due mid-2027, and Lower Nihotupu groundworks are expected from 2027. The plant replacement itself now runs four years past the program's listed end.
Treatment held in few hands
Watercare names Ardmore, Huia and Waikato as its three main plants. Ardmore, which Watercare describes as New Zealand's largest, has a capacity of about 540 ML/d, against average supply of 440 ML/d on the FY2025 base. The Onehunga plant has been out of service since 11 October 2022 because of PFAS, and its NZ$40 million upgrade has slipped two years, with construction now planned for 2027–2029.
Quality holds, mostly
In FY2026 Watercare reported 100% compliance with Taumata Arowai's rules for bacterial, protozoal and chemical water quality and 97.9% for residual disinfection. Real water loss was 11.26%, against 12.8% in FY2025.
How Auckland's dams and river supply hold up in drought, which regulators now set Watercare's revenue, and how its NZ$15.2 billion program will be delivered are covered in the full report. The full report, Water Systems Overview: Watercare Services, is available for USD 499. For a free overview, read the Watercare Services Utility Snapshot.