Watercare opened a Registration of Interest on the Government Electronic Tender Service on 2 September 2026 for alliance partners on its NZ$1.7 billion Waikato Water Supply Programme. Construction is expected to begin in early 2028, with completion targeted for the end of 2033, and no partner has been chosen.
What is being bought
The programme covers a new raw water intake on the Waikato River, increased treatment capacity, about 50 kilometres of pipeline and a 50-megalitre reservoir at Pukekohe West. Watercare describes the Waikato plant as supplying about 20% of Auckland's water, with reliance rising in summer. Dam levels were "uncomfortably low" in March 2025.
A different way of buying
Watercare will deliver the programme through an alliance and says future programmes will be assessed individually for their delivery model. Its FLOW 2026 briefing states that it is focused on the best long-term value, "not simply selecting the lowest-cost bid". Its renewals work runs through standing panels: 19 partners on a NZ$3.5 billion renewals programme.
Pressure to deliver
Watercare invested NZ$959.5 million in FY2026, NZ$90.5 million below target, and forecasts NZ$1,100.0 million in FY2027 and NZ$1,350.0 million in FY2028. Its revenue is capped under the Watercare Charter until 30 June 2028, and the Commerce Commission has said it is keen to inspect plans of about NZ$1.5 billion a year before setting the first price-quality path.
Who decides on Watercare's spending, which contractors already hold its major work, and where suppliers in each category should focus first are covered in the full report. The full report, Watercare Services: Utility Account Brief, is available for USD 499. For a free overview, read the Watercare Services Utility Snapshot.