01
About the Utility
PUB, Singapore’s National Water Agency, is a Singapore Government agency that acts as both the country’s water services provider and its water regulatory authority. Its operations span potable water, NEWater and used water, and it also carries drainage and coastal protection, partly funded through the Government’s Coastal and Flood Protection Fund. Public funding is built into the model: in FY2024 PUB reported government operating grants of $488,696 thousand alongside a net operating loss of $315,544 thousand, and its capital expenditure combines PUB-funded and government-funded spending. Long-term planning traces back to the 1972 Water Master Plan, the blueprint for developing Singapore’s water resources.
02
Water System
Singapore’s supply combines local catchments with climate-resilient sources such as desalinated water and NEWater. Its first reservoirs, MacRitchie, Peirce and Seletar, lie in protected catchments closed to major development, and the wider stormwater network comprises 17 reservoirs and more than 8,000 km of canals and drains. PUB has stated that desalination would meet up to 30% of future water needs by 2060. Demand is projected to almost double by 2065, with non-domestic users taking a growing share. On the network, distribution losses fell to 7.1% in 2024, and every drinking-water test met WHO Guidelines and national regulations from FY2015 to FY2024.
Distribution losses
PUB potable water distribution losses, %, 2019 to 2024 (years as labelled in PUB's ten-year statistical table)
Reported actuals. Distribution Losses replaced the earlier Unaccounted for Water indicator from 2019, so earlier years are not comparable and are not shown.
Sources: PUB Annual and Sustainability Report 2024/25, ten-year statistical table; 2019–2020 also in PUB Annual Report 2020/21.03
Wastewater System
Used water is a core PUB operation alongside potable water and NEWater. The first phase of the Deep Tunnel Sewerage System, completed in 2008, combined a 48km deep tunnel from Kranji to Changi with 60km of link sewers and Changi Water Reclamation Plant. Changi’s expansion, commissioned progressively since 2024, raises treatment capacity from 202 to 246 million gallons per day. The system’s second phase repeats the model with deep tunnels, link sewers and a Tuas plant that includes NEWater treatment. Tuas is integrated with NEA’s Integrated Waste Management Facility and designed to be energy-self-sufficient.
04
Investment & Priorities
PUB’s capital expenditure combines PUB-funded and government-funded spending. The Deep Tunnel Sewerage System’s second phase was about 83% complete at the end of May 2026, with the tunnels finished and Tuas Water Reclamation Plant scheduled for progressive commissioning from 2027. PUB has issued two green bonds totalling $1.125 billion, and its borrowings consist of unsecured fixed-rate bonds. Coastal and drainage works draw on the Coastal and Flood Protection Fund, created in 2020 with an initial $5 billion.
05
Sustainability & Resilience
Climate pressure reaches PUB through both energy and the coast. Greater reliance on desalinated water and NEWater means its energy and emissions footprint could quadruple by 2065. PUB has deployed floating solar and plans to expand rooftop solar by 2030. Demand policy is also tightening: since January 2024, selected water-intensive industries must meet mandatory recycling requirements. Along the coast of a low-lying island, City-East Coast protection moves to design, with construction planned in the 2030s, while ‘Long Island’ is the proposed defence for the East Coast.
06
Key Challenges
- Completing the Deep Tunnel Sewerage System’s second phase and commissioning Tuas Water Reclamation Plant from 2027.
- Meeting demand projected to almost double by 2065 while moving household use towards the 2030 target.
- Containing an energy and emissions footprint that could quadruple as desalination and NEWater grow.
- Protecting low-lying coasts from sea-level rise through long-term coastal investment.
07
Major Projects
Deep Tunnel Sewerage System Phase 2
Deep tunnels, link sewers and the Tuas Water Reclamation Plant with NEWater treatment, integrated with NEA’s waste facility.
- Status / period
- Under construction · about 83% complete (31 May 2026); Tuas commissioning from 2027
- Investment / capacity
- Tuas plant 176 MGD initial capacity
Changi Water Reclamation Plant Phase 2 Expansion
A fifth treatment train, separate wet weather facility and membrane bioreactor technology at the deep-tunnel system’s first plant.
- Status / period
- Progressively commissioned since 2024
- Investment / capacity
- 202 to 246 mgd
City-East Coast Coastal Protection
Coastal protection measures moving from a concluded site-specific study into preliminary and detailed design.
- Status / period
- Design · construction planned in the 2030s