Rome's administrative court (TAR) has annulled the award of Acea's largest water contract, the €1.449 billion doubling of the upper Peschiera aqueduct, after upholding an appeal by Webuild and Seli Overseas, according to a trade report on 19 November 2026. The contract had gone to a grouping led by Eteria Consorzio Stabile, with Itinera, Vianini Lavori, Monaco and Ghella among its members.
A timetable that was already tight
The design-and-build tender, launched in July 2025, set construction from June 2027 and commissioning from April 2034. Acea Ato 2's concession for ATO 2 Lazio Centrale, which serves 3,942,215 residents in 105 municipalities, expires on 31 December 2032. A 2026 Budget Law provision allows an extension of up to 10 years in proportion to Peschiera investment, but no extension had been decided by November 2026.
Who pays
About €850 million of state funding (Il Sole 24 Ore, July 2025) covers part of the cost, alongside €35 million and €15 million earmarked by the 2025 Budget Law. The rest is to come from ATO 2 tariffs, which rose 7.9% from 1 January 2026. The Peschiera–Marcio system supplies 80% of Rome's population, according to Acea's 2025 sustainability statement; Il Sole 24 Ore put it at 70% of Romans' homes in July 2025.
The works already under way
Four related Peschiera-system projects, costing €553.4 million with €150 million from Italy's recovery plan, were under way at the end of 2025. Acea reported overall progress on the new Marcio aqueduct at 71% in 2025.
Whether construction can still start in June 2027, how the concession and the 2026–2027 tariff update line up with a 2034 aqueduct, and how Acea's 2028 targets for losses and reuse are progressing are set out in the full report. The full report, Water Utility of the Future: Acea, is available for USD 499. For a free overview, read the Acea Utility Snapshot.