01
Executive overview
Key findings
€1.449 billion: tender value of the Peschiera aqueduct doubling; the award to an Eteria-led grouping was annulled by the Rome administrative court on appeal (reported 19 November 2026). The tender timetable has construction from June 2027 and commissioning from April 2034
€450 million: EIB package for the 2027–2030 Lazio water program (network reinforcement, leakage reduction, digitalization, reuse); first €200 million tranche signed 27 July 2026
41.61%: 2028 loss target for Acea Ato 2, Acea Ato 5 and GORI combined, from 47.12% in 2023 and 43.99% in 2025
783 districts: measurement districts covering about 72% of the network managed by Acea Ato 2 (2024)
02
Buyer relevance
Who the report is for
Network, metering and leak-detection suppliers
Size the next phase from 783 measurement districts, smart meter objectives of 33,000 and 30,000, and a 2028 loss target of 41.61%.
Civil contractors and engineering firms
Track the Peschiera doubling after the annulled award, against a tender timetable with construction from June 2027.
Lenders, bond investors and rating analysts
Read the Blue Bond, the €450 million EIB package and leverage of 3.49x against a concession that ends in 2032.
Regulators, public bodies and sector advisers
Compare Acea's 2028 targets for losses, reuse and remote control with ARERA's indicators for Acea Ato 2.
03
Decision scope
Questions answered
What is the status of the Peschiera aqueduct doubling?
The €1.449 billion contract was awarded to an Eteria-led grouping, and the Rome administrative court annulled the award on appeal (reported 19 November 2026); the tender timetable had construction from June 2027.
How far has Acea digitized the Rome network?
Acea Ato 2 had 783 measurement districts covering about 72% of the network it manages at the end of 2024, with 3,651 flow and pressure meters active.
What are Acea's 2028 water targets?
Losses of 41.61% across Acea Ato 2, Acea Ato 5 and GORI (43.99% in 2025), reuse of 7 Mm³ a year (3.8 Mm³ in 2025) and 15 MW of solar capacity (2.5 MW in 2025).
How is the program financed?
Through tariffs capped by ARERA to 2029, a €450 million EIB package for 2027–2030, a €500 million Blue Bond at 3.375% and about €850 million of state funding for Peschiera.
Why does the concession matter?
The ATO 2 concession ends on 31 December 2032, before Peschiera commissioning from April 2034; a 2026 law allows an extension of up to 10 years, not yet decided.
04
Inside the report
Inside the complete report
Executive Snapshot
1. From Service Provider to System Operator
2. System Intelligence and Digital Control
3. Energy, Carbon, and Resource Decoupling
4. Infrastructure Strategy for a Non-Stationary Climate
5. Customers, Demand, and the Water Prosumer
6. Governance, Regulation, and Institutional Reform
7. Capital Planning and Financial Architecture
8. Workforce, Capability, and Organisational Change
9. Strategic System Roadmap
Conclusion
Source Register
05
Public preview
What to watch next
2. System Intelligence and Digital Control
Reported results of the PNRR digitalization project after its January 2026 end date; smart meter installations against the stated objectives; ARERA's next determination, showing whether the 2024 and 2025 M1a targets were met.
4. Infrastructure Strategy for a Non-Stationary Climate
Any appeal to the Consiglio di Stato, a new award, or a revised timetable; a completion notice for Marcio lot 1; annual kilometers rehabilitated.
6. Governance, Regulation, and Institutional Reform
A decision under the concession extension law; the 2026–2027 tariff update; the Publiacqua merits appeal; ARERA's next quality incentive results.
7. Capital Planning and Financial Architecture
The next business plan's investment and leverage targets; drawdown of the remaining €250 million of the EIB package (calculated, 450 less 200); the June 2027 refinancing; full-year 2026 results against guidance.
Section 4: the Peschiera doubling, its funding, the PNRR works and the system's share of Rome's supply.

06
Included
What you receive
The complete PDF report: 14 pages, 12 sections, 19 tables and a register of 26 sources.
This edition
November 2026, First edition.
07
Evidence & method
Evidence and method
The report draws on Acea's consolidated financial statements, half-year and nine-month results, the 2025 sustainability statement and Acea Ato 2's own reports, ARERA tariff and quality determinations, EIB and Acea press releases, and press coverage of the Peschiera tender and court ruling.
Sources
26 sources, listed in the report's source register. Evidence current to 24 November 2026. Principal data periods: FY 2025 consolidated results and sustainability statement (year ended 31 December 2025); results to 30 September 2026; Acea Ato 2 sustainability report 2024; ARERA quality determinations for 2019, 2021 and 2023; the MTI-4 tariff period 2024–2029. Project, financing and legal status checked on 24 November 2026. All currency is euros (€).
Evidence boundaries
This report uses authoritative source material available at the stated research cutoff. It distinguishes published facts, calculated values and analytical interpretation. No independent modelling is performed. Forward-looking analysis reflects published plans, documented trends and stated uncertainties. It does not constitute legal, financial, investment or engineering advice.
08
Lead analyst
Robert C. Brears
Founder, Our Future Water Intelligence
Robert C. Brears is a water-security specialist and author whose work examines utility governance, infrastructure investment, climate resilience and long-term water-system change for executive and policy audiences.
- Decision-focused utility intelligence
- Published water-policy author
- Evidence-grounded system analysis
09
Buyer FAQs
Before you purchase
Who can use the report?
Licensed for internal use within one purchasing organization. The PDF and its contents may be shared with colleagues within that organization. External redistribution, resale and public publication are prohibited without permission.
How is the report delivered?
The PDF is available to download immediately after confirmed payment, through our secure delivery system.
Can my organization buy wider access?
Institutional purchasing: For invoice enquiries, multi-organization licensing or broader access requirements, contact Our Future Water Intelligence.
10
Water Utility of the Future: Acea
- Format
- Length
- 14 pages
- Edition
- November 2026, First edition
- Price
- USD 499
11
Report details
Publication details
- Publisher
- Our Future Water Intelligence
- Report family
- Water Utility Intelligence Report
- Edition
- November 2026, First edition
- Format
- Length
- 14 pages
- Reference
- OFW_EXT_WATER_UTILITY_OF_THE_FUTURE_ACEA_34a435fbad06
- Evidence current to
- 24 November 2026
14
Explore this report family
More Water Utility of the Future reports
Explore the same report family covering other utilities.

Water Utility of the Future
Water Utility of the Future: National Water Company
- Geography
- Saudi Arabia, Middle East
- Edition
- November 2026, New edition
- Length
- 12 pages

Water Utility of the Future: Johannesburg Water
- Geography
- City of Johannesburg, Gauteng, South Africa
- Edition
- November 2026, First edition
- Length
- 14 pages

Water Utility of the Future
Water Utility of the Future: Dubai Electricity and Water Authority
- Geography
- Dubai, United Arab Emirates
- Edition
- November 2026, New edition
- Length
- 16 pages