Johannesburg has 43 leaking reservoirs that would cost R1.25 billion to fix, and 15 of them were proposed for repair in the coming year at R652 million, according to May 2026 reporting. The repairs sit inside a wider programme of 44 reservoirs and towers that the Executive Mayor said in July 2026 would add 140 Ml of new capacity and five new towers.
Storage under strain
The need became visible in late 2026. Outages and low pressure began on 19 October 2026, and overall system storage stood at 41% on 2 November. Level 2 water restrictions followed on 21 November 2026.
What is being built
The 26 Ml Brixton Reservoir 2 and its 2 Ml tower opened on 29 April 2026, about a year late. In Midrand, the Erand Tower was 96% built and the 20 Ml Carlswald Reservoir 26% complete in August 2026, with Carlswald expected about July 2027. The Hursthill 2 refurbishment stood at about 20% in July 2026, with its contractor off site over late payment and completion moved to March 2027.
Funding still open
A ZAR 750 million, 15-year IFC loan to the City for reservoir upgrading and pipe replacement showed the status "Hold" on 30 October 2026. Johannesburg Water's five-year capital budget is R13.06 billion for 2026/27 to 2030/31.
Who pays contractors
Since 1 July 2026 the utility has held its own water and sanitation revenue, after cash sweeping to the City stopped on 30 June 2026. Its collection rate was 74.84% in FY2024/25.
How Johannesburg Water buys, which other projects are open or emerging, and where suppliers should focus first are set out in the brief. The full report, Johannesburg Water: Utility Account Brief, is available for USD 499. For a free overview, read the Johannesburg Water Utility Snapshot at https://ourfuturewaterintelligence.com/utilities/johannesburg-water.