Johannesburg Water has four tenders open for the replacement and upgrading of sewer pipelines across its regions, numbered JW 14501, 14503, 14504 and 14505, with notices dated 17 November 2026 and closing dates between 27 January and 4 February 2027.
A programme far behind plan
The utility replaced 14.741 km of sewer and 20.451 km of water pipe in FY2024/25. Its Business Plan 2026/27 plans 346 km of water and 214 km of sewer replacement over five years, with a target of 100 km a year. The Executive Mayor said in July 2026 that R207 million was allocated to citywide sewer replacement this year.
Financing not yet signed
About R13 billion is being sought for pipe replacement, with the DBSA among the lenders engaged but nothing signed as of July 2026. The renewal rate across the network and treatment works was 0.49% by value in FY2024/25, against a target of 2.00% in 2029/30.
Payment risk
Contractors have stopped work over late payment on two projects. The Craigavon sewer rising main contractor in Fourways stopped twice. Its Phase 2, a 3.3 km, 900 mm main, had bids due on 7 August 2026 (last confirmed August 2026), with award the next milestone. Capital spending in the first half of 2025/26 was 18% of the R1.704 billion budget.
A new cash position
Cash sweeping to the City of Johannesburg stopped on 30 June 2026, so the utility now holds its own water and sanitation revenue.
Which other projects are open, emerging or strategic, who already holds major work and what to watch next are covered in the brief. The full report, Johannesburg Water: Utility Account Brief, is available for USD 499. For a free overview, read the Johannesburg Water Utility Snapshot at https://ourfuturewaterintelligence.com/utilities/johannesburg-water.