Muscat Governorate's contracted desalination plants and utility-run plants total about 431,000 m³ a day, against peak demand in Nama PWP's Muscat Zone of 677,000 m³ a day in 2025. That is about 64% of peak and 71% of average demand of 606,000 m³ a day. The rest comes by pipeline from the Barka Zone, which PWP calls "essential to maintain supply balance".
Two plants and two pipelines
Ghubrah II has contracted capacity of 191,000 m³ a day and Qurayyat 200,000 m³ a day, under purchase agreements running to 2034 and 2037. Two small Nama Water Services plants add about 40,000 m³ a day. From Barka, a dedicated line to Aseeb carries 100,000 m³ a day and a line shared with Ad Dakhiliyah up to 312,000 m³ a day, with about 242,000 m³ a day available in 2025.
What 2027 adds
Ghubrah III, a 300,000 m³ a day plant, was 93% complete in November 2026, with operations expected in Q2 2027. The Wadi Dayqah dam purification plant, 57% complete in October 2026, would add 35,000 m³ a day of drinking water, expected in May 2027, although PWP plans for 2028. Together they lift local capacity to about 766,000 m³ a day if existing plants stay in service.
Still short of 2032
PWP projects Muscat Zone peak demand at 774,000 m³ a day by 2032, up from 677,000 in 2025. Even with both new plants, local capacity would sit just below that peak. The Al Ghubrah pumping hub, meant to reach about 490 million litres a day by Q1 2027 to move the new water, is a second deadline in the same chain.
Whether the Barka links stay the swing supply, how the operator change under the Cluster 1 contract affects losses, and what the wastewater and finance pipelines mean for Muscat to 2032 are set out in the full report. The full report, Muscat Water Intelligence Report, is available for USD 799. For a free overview, see https://ourfuturewaterintelligence.com/cities/muscat.