01
Executive overview
Key findings
AED 12,100.3 million: capital expenditure in 2025 (audited segment note); DEWA states it invested AED 11.72 billion
AED 13,026.9 million: future commitments, including capital expenditure, at 31 March 2026
555 → 735 MIGD: desalination capacity at 31 March 2026 and DEWA's plan for 2030 (plan)
402: transmission substations at mid-2026, with 65 new 132 kV substations under construction
02
Buyer relevance
Who the report is for
Water transmission and civil contractors
Approach the lowest bidders on the three Hassyan Phase 2 packages, from AED 335.92 million to AED 792.59 million, before awards are announced.
Desalination EPC and equipment suppliers
Plan for the new Hassyan plant of about 272,000 m3 a day, signed with ACWA Power on 28 October 2026 for operation in October 2029.
Transmission and distribution equipment makers
Size demand from 65 new 132 kV substations under construction, more than 30 planned for tender and 793 new 11 kV substations in H1 2026.
Solar and battery storage suppliers
Follow Solar Park Phase 7, 2,000 MW of solar and 8,400 MWh of storage, where Masdar was reported lowest bidder.
03
Decision scope
Questions answered
How much does DEWA spend on capital projects?
Audited segment capital expenditure was AED 12,100.3 million in 2025, of which AED 7,203.9 million in the core utility and AED 3,877.5 million in independent power and water project companies.
How do suppliers register?
Through DEWA's SAP SRM supplier portal with a trade licence and the owner's or manager's passport; a September 2026 guide states enrolment is free.
Which tenders are closest to award?
Three Hassyan Phase 2 water transmission packages, with lowest bids of AED 335.92 million, AED 792.59 million and AED 608.08 million reported in July–August 2026.
Does local content matter?
DEWA is one of seven Dubai entities adopting the In-Country Value programme launched in May 2025 through the Tasharok platform.
How is DEWA financed?
Borrowings were AED 43,725.0 million at 31 March 2026, and Moody's has rated it A3 with a stable outlook since May 2024.
04
Inside the report
Inside the complete report
1. The Account at a Glance
2. Organisation and Decision-Making
3. Financial Position
4. Priorities and Pressures
5. How DEWA Buys
6. Opportunity Register
7. Commercial Priorities: Where to Focus First
8. Watch List: What to Monitor and What to Do
Source Register
05
Public preview
What to watch next
Hassyan Phase 2 pipeline awards
Three packages with lowest bids totalling AED 1,736.59 million (calculated).
Solar Park Phase 7 award
Sets the developer who will buy modules, inverters and storage for 2,000 MW.
New Hassyan plant financial close and EPC choice
Opens desalination equipment and construction packages for operation in October 2029.
Q3 2026 and FY 2026 results
Show capital expenditure, borrowings and peak demand (the 2025 nine-month results came on 12 November 2025).
The Opportunity Register: projects, procurement status, existing contractors, supplier categories and routes in.

06
Included
What you receive
The complete PDF report: 12 pages, 9 sections, 6 tables and a register of 15 sources.
This edition
October 2026, First edition.
07
Evidence & method
Evidence and method
The brief draws on DEWA's financial statements and results filed on the Dubai Financial Market, Dubai laws on DEWA and private producers, published tender results reported by MEED, Smart Water Magazine and Saudi Gulf Projects, developer disclosures and supplier registration guidance. Status was checked on 30 October 2026.
Sources
15 sources, listed in the report's source register. Evidence current to 30 October 2026. Principal data periods: FY 2024 audited accounts; FY 2025 preliminary results and audited 31 December 2025 balances; Q1 2026 interim accounts; H1 2026 results (12 August 2026). Project and procurement status checked against public sources on 30 October 2026. All currency is UAE dirhams (AED) unless stated..
08
Lead analyst
Robert C. Brears
Founder, Our Future Water Intelligence
Robert C. Brears is a water-security specialist and author whose work examines utility governance, infrastructure investment, climate resilience and long-term water-system change for executive and policy audiences.
- Decision-focused utility intelligence
- Published water-policy author
- Evidence-grounded system analysis
09
Buyer FAQs
Before you purchase
Who can use the report?
Licensed for internal use within one purchasing organization. The PDF and its contents may be shared with colleagues within that organization. External redistribution, resale and public publication are prohibited without permission.
How is the report delivered?
The PDF is available to download immediately after confirmed payment, through our secure delivery system.
Can my organization buy wider access?
Institutional purchasing: For invoice enquiries, multi-organization licensing or broader access requirements, contact Our Future Water Intelligence.
10
Dubai Electricity and Water Authority: Utility Account Brief
- Format
- Length
- 12 pages
- Edition
- October 2026, First edition
- Price
- USD 499
11
Report details
Publication details
- Publisher
- Our Future Water Intelligence
- Report family
- Utility Account Brief
- Edition
- October 2026, First edition
- Format
- Length
- 12 pages
- Reference
- OFW_EXT_DUBAI_ELECTRICITY_AND_WATER_AUTHORITY_UTILITY_ACCOUNT_BRIEF_2e573b8e0920
- Evidence current to
- 30 October 2026
14
Explore this report family
More Utility Account Briefs
Explore the same report family covering other utilities.

Berliner Wasserbetriebe: Utility Account Brief
- Geography
- Berliner Wasserbetriebe
- Edition
- October 2026, First edition
- Length
- 12 pages

Department of Energy, Abu Dhabi Emirate: Utility Account Brief
- Geography
- Department of Energy, Abu Dhabi Emirate
- Edition
- October 2026, First edition
- Length
- 12 pages

Utility Account Brief
Denver Water: Utility Account Brief
- Geography
- Denver, United States
- Edition
- October 2026
- Length
- 10 pages