Intelligence Reports/Water Utility Intelligence Report
Water Utility of the Future: Massachusetts Water Resources Authority cover

Water Utility Intelligence Report

Water Utility of the Future: Massachusetts Water Resources Authority

MWRA's next phase is redundancy, overflow control and energy, not treatment capacity: an about US$2.1 billion tunnel program and an about US$1.3 billion draft overflow plan lie ahead, while FY2026 capital spending of US$226.8 million ran about 40% below budget. Capital financing already takes 55.3% of the FY2026 budget, and staff project near-term water rate increases of around 3.9%.

Geography
Greater Boston, Massachusetts, United States
Evidence current to
9 November 2026
Format
PDF
Length
14 pages
Edition
November 2026, First edition
Price
USD 499
Secure Stripe checkout · your paid edition is delivered privately in this browser.

Paste the caption with your link. Social platforms control how previews appear.

01

Executive overview

Key findings

About US$2.1 billion: Metropolitan Water Tunnel Program estimate; both tunnels operational by 2040 (target; final cost "not yet defined")

US$226.8 million: FY2026 actual capital spending, about 40% below the US$380.3 million budget

About US$1.3 billion: draft Updated CSO Control Plan, designed for zero CSO discharges to the Charles, Mystic and Alewife Brook in a projected 2050 typical rainfall year (draft)

55.3%: share of the FY2026 Current Expense Budget for capital financing (budgeted)

02

Buyer relevance

Who the report is for

Engineering and construction firms in tunnels, wastewater and coastal works

Time bids around South Tunnel bidding in late 2027 and the US$70 million Deer Island Eastern Seawall award planned for FY2027.

Energy developers and equipment suppliers

Size the Deer Island opportunity from a 24.0% own-generation share in FY2025, a CHP projected at 69.3 GWh a year and a US$31 million battery study estimate.

Municipal bond analysts and investors

Weigh 186% and 187% primary coverage in FY2025 against FY2024–FY2028 cap spending forecast at about US$1.1 billion, about US$309 million under the US$1.4 billion cap.

Member community and state policy staff

Follow the draft overflow plan's US$340 million, US$260 million and US$690 million river shares and the lead program's 2032 goal.

03

Decision scope

Questions answered

01

How much is MWRA planning to spend on new water tunnels?

The Metropolitan Water Tunnel Program estimate is about US$2.1 billion, with both tunnels targeted to be operational by 2040; MWRA says the final cost is not yet defined.

02

Is MWRA spending its capital budget?

No. FY2026 capital spending was US$226.8 million, about 40% below the US$380.3 million budget; the FY2027 Final CIP is US$322.1 million.

03

How much of its own electricity does Deer Island produce?

In FY2025 Deer Island produced 34,814,562 kWh of its own electricity against 144,889,154 kWh required, a 24.0% share, down from 34.1% in FY2017.

04

What will the updated overflow plan cost?

The draft Updated CSO Control Plan is about US$1.3 billion in current dollars, designed for zero discharges in a projected 2050 typical rainfall year; the final plan is due in 2027.

04

Inside the report

Inside the complete report

Executive Snapshot

1. From Service Provider to System Operator

2. Energy, Carbon, and Resource Decoupling

3. Infrastructure Strategy for a Non-Stationary Climate

4. Customers, Demand, and the Water Prosumer

5. Governance, Regulation, and Institutional Reform

6. Capital Planning and Financial Architecture

7. Strategic System Roadmap

Conclusion

Source Register

05

Public preview

What to watch next

6. Capital Planning and Financial Architecture

The FY2028 budget and assessment proposal; FY2027 capital spending against the US$322.1 million plan; rating agency commentary at the next bond sale.

7. Strategic System Roadmap

The FY2028–FY2033 capital prioritization; the final CSO plan's cost allocation among communities; South Tunnel procurement documents.

3. Infrastructure Strategy for a Non-Stationary Climate

South Tunnel bidding in late 2027; the Eastern Seawall award in FY2027; Quabbin volume at June 30, 2027.

5. Governance, Regulation, and Institutional Reform

Gulliver's start date; the court's ruling on MWRA's motion; issuance of the final Deer Island permit.

Sample page · page 11 of 14

The Strategic System Roadmap, setting MWRA's overflow, tunnel, energy and lead programs against their milestones from 2026 onward.

Report page with a roadmap table listing MWRA programs by horizon, status and strategic role, and a table of draft overflow plan costs by river.

06

Included

What you receive

The complete PDF report: 14 pages, 10 sections, 18 tables and a register of 26 sources.

This edition

November 2026, First edition.

07

Evidence & method

Evidence and method

The report draws on MWRA's FY2025 annual financial report, its 2026 bond Official Statement and rating agency reports, its FY2024 to FY2027 budgets and capital programs, quarterly performance indicators, the greenhouse gas inventory, and board papers and votes to October 21, 2026.

Sources

26 sources, listed in the report's source register. Evidence current to 9 November 2026. Principal data periods: FY2025 audited results (fiscal years end June 30; FY2025 is the year ended June 30, 2025); FY2026 and FY2027 budgets and capital program; board decisions to October 21, 2026; status checked to November 9, 2026. All currency is US dollars..

Evidence boundaries

This report uses authoritative source material available at the stated research cutoff. It distinguishes published facts, calculated values and analytical interpretation. No independent modelling is performed. Forward-looking analysis reflects published plans, documented trends and stated uncertainties. It does not constitute legal, financial, investment or engineering advice.

08

Lead analyst

Robert C. Brears

Founder, Our Future Water Intelligence

Robert C. Brears is a water-security specialist and author whose work examines utility governance, infrastructure investment, climate resilience and long-term water-system change for executive and policy audiences.

  • Decision-focused utility intelligence
  • Published water-policy author
  • Evidence-grounded system analysis

09

Buyer FAQs

Before you purchase

Who can use the report?

Licensed for internal use within one purchasing organization. The PDF and its contents may be shared with colleagues within that organization. External redistribution, resale and public publication are prohibited without permission.

How is the report delivered?

The PDF is available to download immediately after confirmed payment, through our secure delivery system.

Can my organization buy wider access?

Institutional purchasing: For invoice enquiries, multi-organization licensing or broader access requirements, contact Our Future Water Intelligence.

10

Water Utility of the Future: Massachusetts Water Resources Authority

Format
PDF
Length
14 pages
Edition
November 2026, First edition
Price
USD 499
Secure Stripe checkout · your paid edition is delivered privately in this browser.

11

Report details

Publication details

Publisher
Our Future Water Intelligence
Report family
Water Utility Intelligence Report
Edition
November 2026, First edition
Format
PDF
Length
14 pages
Reference
OFW_EXT_WATER_UTILITY_OF_THE_FUTURE_MASSACHUSETTS_WATER_RESOURCES_AUTHORITY_b51d402dd9bf
Evidence current to
9 November 2026

14

Explore this report family

More Water Utility of the Future reports

Explore the same report family covering other utilities.

Water Utility of the Future: Berliner Wasserbetriebe cover

Water Utility of the Future

Water Utility of the Future: Berliner Wasserbetriebe

Analysis of Berliner Wasserbetriebe’s infrastructure investment, water resilience and treatment priorities, connecting operating performance with the decisions shaping Berlin’s future water services.
Geography
Berlin, Germany
Edition
2026 · v3
Length
19 pages
Explore report

Stay informed

Our Future Water Intelligence updates

New analysis, water intelligence and report releases, delivered by email.